CYCLIC SCHEDULING TO MINIMIZE INVENTORY IN A BATCH FLOW LINE

被引:25
作者
DOBSON, G [1 ]
YANO, CA [1 ]
机构
[1] UNIV MICHIGAN,DEPT IND & OPERAT ENGN,ANN ARBOR,MI 48109
关键词
D O I
10.1016/0377-2217(94)90087-6
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper addresses the problem of determining a cyclic schedule for batch production on a flow line. We assume a constant supply of raw materials and a constant demand for all finished goods. Material that has completed processing at one stage is transferred to the next stage in small transfer batches. Inventory may be held before the line, at the end of the line, or between any pair of adjacent stations. The objective is to find a sequence of production and a cycle length that minimize the average cost per unit time of holding inventory. A linear programming formulation is given that determines the optimal cycle length and finishing times for a given set of sequences, one for each machine. Two heuristics are presented for finding near-optimal sequences: one is applicable to the special case of a two-machine flow line;the others are applicable to an m-machine line and focus on different aspects of the problem (e.g., cycle stock or work-in-process inventory). From a computational study, we have observed that: 1) permutation schedules, i.e., schedules with the same sequence on all machines, are nearly always optimal, 2) the heuristics produce near optimal solutions, 3) the batching decision, i.e., the choice of cycle length, is substantially more significant than the sequencing decision for minimizing inventory costs.
引用
收藏
页码:441 / 461
页数:21
相关论文
共 15 条
[1]   THE ECONOMIC LOT-SCHEDULING PROBLEM - ACHIEVING FEASIBILITY USING TIME-VARYING LOT SIZES [J].
DOBSON, G .
OPERATIONS RESEARCH, 1987, 35 (05) :764-771
[2]  
ELNAJDAWI MK, 1990, COMMON CYCLE SCHEDUL
[3]  
ELNAJDAWI MK, 1989, THESIS U PENNSYLVANI
[4]   AN EXTENSION TO THE CLASS OF EASY ECONOMIC LOT SCHEDULING PROBLEMS [J].
GALLEGO, G .
IIE TRANSACTIONS, 1990, 22 (02) :189-190
[5]  
HANSSMANN F, 1962, OPERATIONS RES PRODU
[6]   COMMON CYCLE SCHEDULING IN A MULTISTAGE PRODUCTION PROCESS [J].
HSU, JIS ;
ELNAJDAWI, M .
ENGINEERING COSTS AND PRODUCTION ECONOMICS, 1990, 20 (01) :73-80
[7]  
Jensen P. A., 1972, AIIE T, V4, P126
[8]   WHEN IS THE ECONOMIC LOT SCHEDULING PROBLEM EASY [J].
JONES, PC ;
INMAN, RR .
IIE TRANSACTIONS, 1989, 21 (01) :11-20
[9]  
MATSUO H, 1990, NAV RES LOG, V37, P679, DOI 10.1002/1520-6750(199010)37:5<679::AID-NAV3220370507>3.0.CO
[10]  
2-Q