Is public-private partnership a panacea for infrastructure development? The case of Beijing National Stadium

被引:27
作者
Ke, Yongjian [1 ]
机构
[1] Univ Newcastle, Sch Architecture & Built Environm, Callaghan, NSW 2308, Australia
关键词
public-private partnership; Beijing National Stadium; social infrastructure; China;
D O I
10.1080/15623599.2014.899127
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Public-private partnership (PPP) is such a hot concept that nowadays it is discussed everywhere be it a public sector management journal or a public sector management conference. Governments subject to severe fiscal pressure in developing countries like China, where PPP law is not in place yet, regard it as a panacea or fixed solution for infrastructure development. This paper hence attempts to provide reference to this point by investigating the Beijing National Stadium. There was a significant change in the Project Company on 20 August 2009. Three main reasons for the contract change were (1) wrong identification of the retractable roof as one of the output specifications, (2) adoption of PPP without a careful feasibility study and (3) strong government interference like suspension of selling name-right and prohibition of holding small-scale or small events. It was found that PPP would not be more appropriate than conventional procurement in this project. It was therefore proved that PPP is not a panacea for infrastructure development. It is expected that a review of the Beijing National Stadium can provide valuable information for when and how to implement PPPs. More considerations on receiving value for money in the whole project lifecycle (including the operation) should be taken in a PPP project.
引用
收藏
页码:90 / 100
页数:11
相关论文
共 52 条
[1]   Risk-Neutral Pricing Approach for Evaluating BOT Highway Projects with Government Minimum Revenue Guarantee Options [J].
Ashuri, B. ;
Kashani, H. ;
Molenaar, K. R. ;
Lee, S. ;
Lu, J. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2012, 138 (04) :545-557
[2]   Critical Success Factors for PPPs in Infrastructure Developments: Chinese Perspective [J].
Chan, Albert P. C. ;
Lam, Patrick T. I. ;
Chan, Daniel W. M. ;
Cheung, Esther ;
Ke, Yongjian .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2010, 136 (05) :484-494
[3]   Potential Obstacles to Successful Implementation of Public-Private Partnerships in Beijing and the Hong Kong Special Administrative Region [J].
Chan, Albert P. C. ;
Lam, Patrick T. I. ;
Chan, Daniel W. M. ;
Cheung, Esther ;
Ke, Yongjian .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2010, 26 (01) :30-40
[4]   Can the pilot BOT Project provide a template for future projects? A case study of the Chengdu No. 6 Water Plant B Project [J].
Chen, Chuan .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (06) :573-583
[5]  
Cheung E, 2009, J PROP INVEST FINANC, V27, P290, DOI 10.1108/14635780910951984
[6]   THE PUBLIC SECTOR'S PERSPECTIVE ON PROCURING PUBLIC WORKS PROJECTS - COMPARING THE VIEWS OF PRACTITIONERS IN HONG KONG AND AUSTRALIA [J].
Cheung, Esther ;
Chan, Albert P. C. ;
Kajewski, Stephen .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2010, 16 (01) :19-32
[7]  
China VR, 2003, ASSESSMENT EXHIBITIO
[8]  
Cooper D. F., 2005, PROJECT RISK MANAGEM
[9]  
Du XL, 2008, CO FLAP BIRDS NEST N
[10]  
Efficiency Unit, 2008, INTR GUID PUBL PRIV