PERFORMANCE OF MASONRY BUILDINGS AND CHURCHES IN THE 22 FEBRUARY 2011 CHRISTCHURCH EARTHQUAKE

被引:110
作者
Dizhur, Dmytro [1 ]
Ingham, Jason [1 ]
Moon, Lisa [2 ]
Griffith, Mike [2 ]
Schultz, Arturo [3 ]
Senaldi, Ilaria [4 ]
Magenes, Guido [5 ]
Dickie, Jocelyn [6 ]
Lissel, Shelley [6 ]
Centeno, Jose [7 ]
Ventura, Carlos [7 ]
Leite, Joao [8 ]
Lourenco, Paulo [8 ]
机构
[1] Univ Auckland, Dept Civil & Environm Engn, Auckland, New Zealand
[2] Univ Adelaide, Sch Civil Environm & Min Engn, Adelaide, SA, Australia
[3] Univ Minnesota, Dept Civil Engn, Minneapolis, MN 55455 USA
[4] Ctr Postgrad Training & Res Earthquake Engn & Eng, ROSE Sch, Pavia, Italy
[5] Univ Pavia, Dept Struct Mech, Pavia, Italy
[6] Univ Calgary, Dept Civil Engn, Calgary, AB, Canada
[7] Univ British Columbia, Dept Civil Engn, Vancouver, BC, Canada
[8] Univ Minho, Dept Civil Engn, Guimaraes, Portugal
来源
BULLETIN OF THE NEW ZEALAND SOCIETY FOR EARTHQUAKE ENGINEERING | 2011年 / 44卷 / 04期
基金
美国国家科学基金会;
关键词
D O I
10.5459/bnzsee.44.4.279-296
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
As part of the, Project Masonry. Recovery Project funded by the New Zealand Natural Hazards Research Platform, commencing in March 2011, an international team of researchers was deployed to document and interpret the observed earthquake damage to masonry buildings and to churches as a result of the 22nd February 2011 Christchurch earthquake. The study focused on investigating commonly encountered failure patterns and collapse mechanisms. A brief summary of activities undertaken is presented, detailing the observations that were made on the performance of and the deficiencies that contributed to the damage to approximately 650 inspected unreinforced clay brick masonry (URM) buildings, to 90 unreinforced stone masonry buildings, to 342 reinforced concrete masonry (RCM) buildings, to 112 churches in the Canterbury region, and to just under 1100 residential dwellings having external masonry veneer cladding. In addition, details are provided of retrofit techniques that were implemented within relevant Christchurch URM buildings prior to the 22nd February earthquake and brief suggestions are provided regarding appropriate seismic retrofit and remediation techniques for stone masonry buildings.
引用
收藏
页码:279 / 296
页数:18
相关论文
共 19 条
[1]  
[Anonymous], 2008, NTC 2008 NORM TECN C
[2]  
ASCE, 2006, AM SOC CIVIL ENG
[3]  
ASTM, 2003, E48896 ASTM INT
[4]   Learning from Construction Failures due to the 2009 L'Aquila, Italy, Earthquake [J].
Augenti, N. ;
Parisi, F. .
JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES, 2010, 24 (06) :536-555
[5]  
BINDA L, 1994, PROCEEDINGS OF THE 10TH INTERNATIONAL BRICK AND BLOCK MASONRY CONFERENCE, VOLS 1-3, P539
[6]  
Borri A., 2008, 6 INT C STRUCT AN HI
[7]  
Canterbury Earthquake Recovery Authority (CERA), 2011, DEM LISTS
[8]  
Dizhur D., 2010, PERFORMANCE UNREINFO
[9]   PERFORMANCE OF UNREINFORCED AND RETROFITTED MASONRY BUILDINGS DURING THE 2010 DARFIELD EARTHQUAKE [J].
Dizhur, Dmytro ;
Ismail, Najif ;
Knox, Charlotte ;
Lumantarna, Ronald ;
Ingham, Jason M. .
BULLETIN OF THE NEW ZEALAND SOCIETY FOR EARTHQUAKE ENGINEERING, 2010, 43 (04) :321-339
[10]  
Dolce M., 2001, P 7 INT SEM SEISM IS