Evaluating the project success index of public-private partnership projects in Hong Kong: The case of the Cross Harbour Tunnel

被引:17
作者
Osei-Kyei, Robert [1 ]
Chan, Albert P. C. [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Bldg & Real Estate, Hong Kong, Hong Kong, Peoples R China
来源
CONSTRUCTION INNOVATION-ENGLAND | 2018年 / 18卷 / 03期
关键词
Hong Kong; PPP; Public-private partnerships; Fuzzy synthetic evaluation; Cross-Harbour Tunnel; Project success index;
D O I
10.1108/CI-08-2017-0067
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Purpose Since 1960, many public-private partnership (PPP) projects have been implemented in Hong Kong. Some projects have been considered as very successful, whereas others are seen as less successful. Unfortunately, these success outcomes have remained abstract because they are not in quantifiable terms. This paper aims to develop a model that can quantify the success outcome of PPP projects in Hong Kong. Design/methodology/approach Both quantitative and qualitative research approaches were adopted for the study. First, a questionnaire survey was conducted with PPP practitioners in Hong Kong, and thereafter, the fuzzy synthetic evaluation technique was used to develop a project success index for PPP projects in Hong Kong. The Hong Kong Cross-Harbour Tunnel project was used as a case study to demonstrate the applicability of the pragmatic model. Findings The success index model developed consists of four unrelated success criteria groupings: cost effectiveness, quality of services and technical specification, environmental impact and long-term partnership. Further, the computed success index for the Cross-Harbour Tunnel project is 4.06, which indicates that the tunnel project has been highly successful. Originality/value The outputs of this study will enable PPP practitioners in Hong Kong to reliably evaluate the success levels of their projects. In addition, local practitioners can now compare the success levels of two or more PPP projects on the same basis.
引用
收藏
页码:371 / 391
页数:21
相关论文
共 59 条
  • [31] Mak C. K., 2005, SOME ASPECTS PPP APP
  • [32] Critical Success Factors for Transfer-Operate-Transfer Urban Water Supply Projects in China
    Meng, Xianhai
    Zhao, Qi
    Shen, Qiping
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2011, 27 (04) : 243 - 251
  • [33] Use of key performance indicators for PPP transport projects to meet stakeholders' performance objectives
    Mladenovic, Goran
    Vajdic, Nevena
    Wuendsch, Bjorn
    Temeljotov-Salaj, Alenka
    [J]. BUILT ENVIRONMENT PROJECT AND ASSET MANAGEMENT, 2013, 3 (02) : 228 - 249
  • [34] Developing a Project Success Index for Public-Private Partnership Projects in Developing Countries
    Osei-Kyei, Robert
    Chan, Albert P. C.
    [J]. JOURNAL OF INFRASTRUCTURE SYSTEMS, 2017, 23 (04)
  • [35] Comparative Analysis of the Success Criteria for Public-Private Partnership Projects in Ghana and Hong Kong
    Osei-Kyei, Robert
    Chan, Albert P. C.
    [J]. PROJECT MANAGEMENT JOURNAL, 2017, 48 (04) : 80 - 92
  • [36] Osei-Kyei R, 2017, J FACIL MANAG, V15, P90, DOI 10.1108/JFM-07-2016-0032
  • [37] CRITICAL SUCCESS CRITERIA FOR PUBLIC-PRIVATE PARTNERSHIP PROJECTS: INTERNATIONAL EXPERTS' OPINION
    Osei-Kyei, Robert
    Chan, Albert P. C.
    Javed, Arshad Ali
    Ameyaw, Ernest Effah
    [J]. INTERNATIONAL JOURNAL OF STRATEGIC PROPERTY MANAGEMENT, 2017, 21 (01) : 87 - 100
  • [38] Developing Transport Infrastructure in Sub-Saharan Africa through Public-Private Partnerships: Policy Practice and Implications
    Osei-Kyei, Robert
    Chan, Albert P. C.
    [J]. TRANSPORT REVIEWS, 2016, 36 (02) : 170 - 186
  • [39] Reasons for adopting Public-Private Partnership (PPP) for construction projects in Ghana
    Robert, Osei-Kyei
    Dansoh, Ayirebi
    Ofori-Kuragu, J. K.
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2014, 14 (04) : 227 - 238
  • [40] Fuzzy synthetic evaluation of disinfection by-products - a risk-based indexing system
    Sadiq, R
    Rodriguez, MJ
    [J]. JOURNAL OF ENVIRONMENTAL MANAGEMENT, 2004, 73 (01) : 1 - 13