A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM

被引:383
作者
DEMEULEMEESTER, E
HERROELEN, W
机构
关键词
PROJECT MANAGEMENT RESOURCE CONSTRAINTS; PROGRAMMING BRANCH-AND-BOUND; NETWORKS GRAPHS APPLICATIONS;
D O I
10.1287/mnsc.38.12.1803
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In this paper a branch-and-bound procedure is described for scheduling the activities of a project of the PERT/CPM variety subject to precedence and resource constraints where the objective is to minimize project duration. The procedure is based on a depth-first solution strategy in which nodes in the solution tree represent resource and precedence feasible partial schedules. Branches emanating from a parent node correspond to exhaustive and minimal combinations of activities, the delay of which resolves resource conflicts at each parent node. Precedence and resource-based bounds described in the paper are combined with new dominance pruning rules to rapidly fathom major portions of the solution tree. The procedure is programmed in the C language for use on both a mainframe and a personal computer. The procedure has been validated using a standard set of test problems with between 7 and 50 activities requiring up to three resource types each. Computational experience on a personal computer indicates that the procedure is 11.6 times faster than the most rapid solution procedure reported in the literature while requiring less computer storage. Moreover, problems requiring large amounts of computer time using existing approaches for solving this problem type are rapidly solved with our procedure using the dominance rules described, resulting in a significant reduction in the variability in solution times as well.
引用
收藏
页码:1803 / 1818
页数:16
相关论文
共 29 条
[1]  
ALVAREZVALDES R, 1989, ADV PROJECT SCHEDULI, pCH5
[2]  
BALAS E, 1970, APPLICATIONS MATH PR
[3]  
BELL CE, 1990, NAV RES LOG, V37, P61, DOI 10.1002/1520-6750(199002)37:1<61::AID-NAV3220370104>3.0.CO
[4]  
2-S
[5]  
Bellman R., 1982, MATH ASPECTS SCHEDUL
[6]   SCHEDULING SUBJECT TO RESOURCE CONSTRAINTS - CLASSIFICATION AND COMPLEXITY [J].
BLAZEWICZ, J ;
LENSTRA, JK ;
KAN, AHGR .
DISCRETE APPLIED MATHEMATICS, 1983, 5 (01) :11-24
[7]   PROJECT SCHEDULING WITH RESOURCE CONSTRAINTS - A BRANCH AND BOUND APPROACH [J].
CHRISTOFIDES, N ;
ALVAREZVALDES, R ;
TAMARIT, JM .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1987, 29 (03) :262-273
[8]   HEURISTICS FOR SCHEDULING RESOURCE CONSTRAINED PROJECTS - EXPERIMENTAL INVESTIGATION [J].
COOPER, DF .
MANAGEMENT SCIENCE, 1976, 22 (11) :1186-1194
[9]  
Davis E. W., 1973, AIIE T, V5, P297
[10]  
DAVIS EW, 1966, J IND ENGINEERING, V17, P177