Optimizing strategy for repetitive construction projects within multi-mode resources

被引:13
作者
Aziz, Remon Fayek [1 ]
机构
[1] Alexandria Univ, Fac Engn, Struct Engn Dept, Alexandria, Egypt
关键词
Tendering; Construction repetitive projects; Line Of Balance; Cash flow; Net present value; Mathematical modeling and multi-objective optimization;
D O I
10.1016/j.aej.2012.11.003
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Estimating tender data for specific project is the most essential part in construction areas as of a contractor's view such as: proposed project duration with corresponding gross value and cash flows. Cash flow analysis of construction projects has a long history and has been an important topic in construction management. Determination of project cash flows is very sensitive, especially for repetitive construction projects. This paper focuses on how to calculate tender data for repetitive construction projects such as: project duration, project cost, project/bid price, project cash flows, project maximum working capital and project net present value that is equivalent to net profit at the beginning of the project. A simplified multi-objective optimization formulation will be presented that creates best tender data to contractor comparing with more feasible options that are generated from multimode resources in a given project. This mathematical formulation is intended to give more scenarios which provide a practical support for typical construction contractors who need to optimize resource utilization in order to minimize project duration, project/bid price and project maximum working capital while maximizing its net present value simultaneously. At the end of the paper, an illustrative example will be presented to demonstrate the applications of proposed technique to an optimization expressway of repetitive construction project. (C) 2013 Faculty of Engineering, Alexandria University. Production and hosting by Elsevier B.V. All rights reserved.
引用
收藏
页码:67 / 81
页数:15
相关论文
共 51 条
[1]  
Abdel-Khalek H., 2011, INT C INN ENG MAN TE, V59, P289
[2]  
Al-Joburi K., J MANAGEMENT ENG
[3]   Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows [J].
Ammar, Mohammad A. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (01) :65-71
[4]  
Bierman H., 1988, CAPITAL BUDGETING DE
[5]  
Boussabaine A, 1998, CONSTR MANAG ECON, P471, DOI DOI 10.1080/014461998372240
[6]  
Calvert RE., 1986, INTRO BUILDING MANAG, V5th ed
[7]   Evolutionary fuzzy decision model for cash flow prediction using time-dependent support vector machines [J].
Cheng, Min-Yuan ;
Roy, Andreas F. V. .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2011, 29 (01) :56-65
[8]   Evolutionary support vector machine inference system for construction management [J].
Cheng, Min-Yuan ;
Wu, Yu-Wei .
AUTOMATION IN CONSTRUCTION, 2009, 18 (05) :597-604
[9]  
Christenson C., 1955, ACCOUNT REV, P666
[10]  
Cooke B., 1986, COST FINANCIAL CONTR, P25