Risk management practices of contractors: a case study of power station projects in Egypt

被引:11
作者
Hassanein, Amr [1 ]
Afify, Halaa [1 ]
机构
[1] Amer Univ Cairo, Construct Engn, Cairo, Egypt
关键词
risk management; risk identification; construction contracts; risk checklist;
D O I
10.1108/13664380780001102
中图分类号
F8 [财政、金融];
学科分类号
0202 ;
摘要
This research aimed at identifying the most significant risks relevant to construction contracts of two power station projects in Egypt. These were large scale, fast-track projects where a multi-package contracting plan was utilized. Further, the study investigated how risks were perceived and managed by a large sample of Egyptian and international contractors who participated in the execution of these two major projects. A checklist of risk categories was developed to aid contractors in their risk identification effort. The compilation of this checklist identified the following risk categories: 1) owner's obligations; 2) interface with other contractors; 3) liability risks; 4) financial risks; 5) risks related to changes; 6) technical risks and 7) consortium risks. Research results identified a marked lack of consistency in the contractors' risk identification effort. Contractors possessing past experience in Egypt were far better able to identify the relevant risks. On the other hand, local Egyptian contractors with vast experience in Egypt but limited project management experience were shown to lack the necessary expertise to properly identify risks and to take the appropriate exceptions. Furthermore, the results revealed that bidders do not include in their proposals their "true" lists of exceptions which represent genuine risks to them.
引用
收藏
页码:165 / +
页数:16
相关论文
共 15 条
  • [1] Akintoye A.S., 1997, INT J PROJ MANAG, V15, P31, DOI [10.1016/S0263-7863(96)00035-X, DOI 10.1016/S0263-7863(96)00035-X]
  • [2] Bubshait A. A., 1994, INT J PROJ MANAG, V12, P133, DOI [DOI 10.1016/0263-7863(94)90027-2, 10.1016/0263-7863(94)90027-2]
  • [3] Chapman C., 1997, INT J PROJ MANAG, V15, P273, DOI DOI 10.1016/S0263-7863(96)00079-8
  • [4] Charoenngam C., 1999, INT J PROJ MANAG, V17, P9
  • [5] Integrated methodology for project risk management
    del Caño, A
    de la Cruz, MP
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2002, 128 (06) : 473 - 485
  • [6] Risk assessment model of tendering for Chinese building projects
    Fang, DP
    Fong, PSW
    Li, MG
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2004, 130 (06): : 862 - 868
  • [7] Hayes W., 1987, RISK MANAGEMENT ENG
  • [8] Ibbs W., 1986, DETERMINING IMPACT V
  • [9] Lam P., 1999, INT J PROJ MANAG, V17, P77, DOI DOI 10.1016/S0263-7863(98)00017-9
  • [10] Rao Tummala V. M., 1999, International Journal of Project Management, V17, P223, DOI 10.1016/S0263-7863(98)00038-6