Reliability analysis of drum shearer machine at mechanized longwall mines

被引:56
作者
Hoseinie, Seyed [1 ]
Ataei, Mohammad [2 ]
Khalokakaie, Reza [2 ]
Ghodrati, Behzad [3 ]
Kumar, Uday [3 ]
机构
[1] Hamedan Univ Technol, Fac Min Engn, Hamadan, Iran
[2] Shahrood Univ Technol, Fac Min Petr & Geophys, Shahrood, Iran
[3] Lulea Univ Technol, Div Operat & Maintenance Engn, Lulea, Sweden
关键词
Longwall mining; Drum shearer; Reliability; Failure rate; Mean time between failures; Mining; Mining industry; Mining equipment; Product reliability; Failure (mechanical);
D O I
10.1108/13552511211226210
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose - Longwall mining is a special mining method with high productivity and smooth operation and the drum shearer is known as the most important component in longwall mines due to its direct role in the coal cutting and production process. Therefore, its reliability is important in keeping the mine production at a desired level. Hence, reliability analysis is essential in identifying and removing existing problems of this machine in order to achieve a better production condition. This paper seeks to learn about the reliability of the shearer machine in order to locate critical subsystems. The improvement of the reliability of the critical subsystems, to enhance the optimum operation of the shearer machine, is the main objective of this research. Design/methodology/approach - A basic methodology was used in this paper for the reliability modeling of the shearer machine. First, failure and performance data from a two-year period at the Tabas Coal Mine-Iran was classified and sorted. The tests for validating the assumption of independent and identical distribution (iid) of TBF data are done and the best modeling method for each subsystem was selected among the renewal process, homogeneous Poisson process and non-homogeneous Poisson process. Finally, the reliability of subsystems and the machine were assessed. Findings - The study revealed that six important subsystems of the shearer machine are; water system, haulage, electrical system, hydraulic system, cutting arms, and cable system. Pareto analysis shows that the 30 percent of failures and stoppages of the shearer were related to the water system and this system is the most critical subsystem of the machine. The failure rate analysis shows that the failure rates of the hydraulic, haulage and electrical systems were decreasing, meanwhile, the failure rates of the water system, cutting arms and cable system were increasing. The reliability of drum shearer reaches the zero value after 100 hours. Originality/value - This paper, for the first time, defines a practical set of subsystems for the coal shearer based on field data and machine design.
引用
收藏
页码:98 / +
页数:23
相关论文
共 60 条
  • [1] Altshuler V., 1969, SOVIET MINING SCI, V5, P72
  • [2] [Anonymous], 1981, MILHDBK189 ITN DRDCO
  • [3] Ascher H., 1984, REPAIRABLE SYSTEM RE
  • [4] Barabady J., 2007, INT J PERFORMABILITY, V3, P319
  • [5] Reliability analysis of mining equipment: A case study of a crushing plant at Jajarm Bauxite Mine in Iran
    Barabady, Javad
    Kumar, Uday
    [J]. RELIABILITY ENGINEERING & SYSTEM SAFETY, 2008, 93 (04) : 647 - 653
  • [6] Birolini A., 2007, RELIABILITY ENG THEO
  • [7] Blischke W.R., 2003, CASE STUDIES RELIABI
  • [8] OPERATIONAL RELIABILITY OF CONVEYOR LINES WITH INTERMEDIATE STORAGE CAPACITY
    BONDAR, SA
    MERNOV, VV
    [J]. SOVIET MINING SCIENCE USSR, 1979, 15 (03): : 268 - 270
  • [9] Butorin Y.M., 1976, SOVIET MINING, V12, P62, DOI DOI 10.1007/BF02497617
  • [10] Daneshmend LK., 2003, INT J SURFMIN RECLAM, V17, P139, DOI [10.1076/ijsm.17.3.139.14773, DOI 10.1076/IJSM.17.3.139.14773]