Analysis of a Modular Housing Production System Using Simulation

被引:0
作者
Ali, Souma Alhaj [1 ]
Abu Hammad, Ayman [2 ]
Hastak, Mark [3 ]
Syal, Matt [4 ]
机构
[1] Hashemite Univ, Ind Engn Dept, Zarqa, Jordan
[2] Appl Sci Univ, Coll Engn, Dept Civil Engn, Amman, Jordan
[3] Purdue Univ, Sch Civil Engn, W Lafayette, IN 47907 USA
[4] Michigan State Univ, Construct Management Program, E Lansing, MI USA
关键词
Modular Housing; Simulation; Productivity; Construction Operations; Factory Layout; Production Line;
D O I
暂无
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
This paper presents the development of a simulation model for an existing modular housing factory. The activities of the system under study were mapped out, and the process time and total cycle time data of approximately 20 cycles were collected for all activities at the assembly and subassembly stations. Modeling assumptions were determined based on the real system constraints that were observed during the data collection process. The observed constraints included types and sizes of housing units produced and the ways these various types were processed through the system. The model was verified by observing the animation of the entities at a low speed run after each development committed on the model to check that entities are directed through the correct logic. The model was validated by comparing the production output of the model performance measures with the real system outputs. The run results showed a bottleneck free system with average queue time at stations one to station three of 60, 5, and 3.6 minutes respectively over a one week of operation, which is considered to be insignificant. The simulation model provides an efficient tool for production managers to evaluate and analyze the MH production system i) decide the appropriate product mix batch sizes and ii) locate potential bottlenecks hindering the productivity. (C) 2010 Jordan Journal of Mechanical and Industrial Engineering. All rights reserved
引用
收藏
页码:256 / 269
页数:14
相关论文
共 17 条
[1]  
Abu Hammad A., 2002, ASCE CIV ENG C EXP W
[2]  
Aho A. V., 1974, DESIGN ANAL COMPUTER
[3]  
Allen G. F., 1999, J PROPERTY MANAGEMEN, P46
[4]  
[Anonymous], BUILDING TOMORROW MO
[5]  
Hammad A. A., 2004, J ARCHIT ENG, V10, P136, DOI [10.1061/(asce)1076-0431(2004)10:4(136), DOI 10.1061/(ASCE)1076-0431(2004)10:4(136)]
[6]  
Kelton D. W., 1998, SIMULATION ARENA
[7]   USING A MODEL AND EMPIRICAL-DATA TO ANALYZE MANUFACTURED HOME CONSERVATION RETROFITS [J].
LEE, A ;
ENGLIN, J .
ENERGY AND BUILDINGS, 1989, 13 (01) :73-83
[8]  
Markowitz HM, 1979, SIMSCRIPT PAST PRESE
[9]  
Mehrotra N., 2002, MANUFACTURED HOUSING
[10]  
MHI Manufactured Housing Institute, 2009, TRENDS INF MAN HOUS