Development of a conceptual team integration performance index for alliance projects

被引:26
|
作者
Ibrahim, Che Khairil Izam Che [1 ]
Costello, Seosamh B. [1 ]
Wilkinson, Suzanne [1 ]
机构
[1] Univ Auckland, Dept Civil & Environm Engn, Auckland 1142, New Zealand
关键词
Delphi method; key indicators; New Zealand; project alliance; team integration;
D O I
10.1080/01446193.2013.854399
中图分类号
F [经济];
学科分类号
02 ;
摘要
Project alliancing, also known as collaborative contracting, is designed to foster integration practice between multidisciplinary teams involved in delivering construction projects. If continuous improvement in project alliances is to be achieved through the use of integrated teams, a means of assessing how well teams integrate and how that integration changes over time needs to be introduced. As part of a wider study to develop an assessment tool for team integration in road construction alliance projects, key indicators (KIs) are identified for measuring team integration practice. It is necessary to identify not only the relevant KIs, but also which indicators are dominant, thereby focusing the attention of owners and non-owner participants (NOPs) on those that will have the greatest impact on alliance team integration. Seventeen experienced road construction alliance practitioners participated in four rounds of a Delphi questionnaire to identify the KIs. The resulting seven team integration practice KIs were: team leadership; trust and respect; a single team focus on project objectives and key result areas (KRAs); collective understanding; commitment from project alliance board; creation of single and co-located alliance team; and free flow communication. A conceptual alliance team integration performance index (ATIPI) was then developed based on the identified KIs and their relative significance. The ATIPI takes the form of a linear additive weighting model, consisting of a measure for each of the identified KIs and a corresponding weighting coefficient, identified as part of this research. A linear additive weighting model is considered appropriate based on the lack of correlation between the KIs, thus suggesting that they can be considered as independent variables in the ATIPI. The measures for each KI will be determined as part of future research and will result in a fully working model for the ATIPI.
引用
收藏
页码:1128 / 1143
页数:16
相关论文
共 14 条
  • [1] Application of a team integration performance index in road infrastructure alliance projects
    Ibrahim, Che Khairil Izam Che
    Costello, Seosamh B.
    Wilkinson, Suzanne
    BENCHMARKING-AN INTERNATIONAL JOURNAL, 2016, 23 (05) : 1341 - 1362
  • [2] Development of an assessment tool for team integration in alliance projects
    Ibrahim, Che Khairil Izam Che
    Costello, Seosamh B.
    Wilkinson, Suzanne
    INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2015, 8 (04) : 813 - 827
  • [3] Establishment of Quantitative Measures for Team Integration Assessment in Alliance Projects
    Ibrahim, Che Khairil Izam Che
    Costello, Seosamh B.
    Wilkinson, Suzanne
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (05)
  • [4] A Fuzzy Approach to Developing Scales for Performance Levels of Alliance Team Integration Assessment
    Ibrahim, Che Khairil Izam Che
    Costello, Seosamh B.
    Wilkinson, Suzanne
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (05)
  • [5] Key indicators influencing the management of team integration in construction projects
    Ibrahim, Che Khairil Izam Che
    Costello, Seosamh B.
    Wilkinson, Suzanne
    INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2015, 8 (02) : 300 - 323
  • [6] Making sense of team integration practice through the "lived experience" of alliance project teams
    Che Ibrahim, Che Khairil Izam
    Costello, Seosamh B.
    Wilkinson, S.
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2018, 25 (05) : 598 - 622
  • [7] Key Practice Indicators of Team Integration in Construction Projects: A Review
    Ibrahim, Che Khairil Che
    Costello, Seosamh Benedict
    Wilkinson, Suzanne
    CONSTRUCTION AND PROJECT MANAGEMENT, ICCPM 2011, 2011, 15 : 230 - 235
  • [8] Key practice indicators of team integration in construction projects: a review
    Ibrahim, Khairil
    Costello, Seosamh
    Wilkinson, Suzanne
    TEAM PERFORMANCE MANAGEMENT, 2013, 19 (3-4) : 132 - +
  • [9] Development of a partnering performance index (PPI) for construction projects in Hong Kong: a Delphi study
    Yeung, John F. Y.
    Chan, Albert P. C.
    Chan, Daniel W. M.
    Li, Leong Kwan
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2007, 25 (12) : 1219 - 1237
  • [10] Relationships among internal stakeholders in construction projects: A cognitive evaluation for sustainable team integration in Nigeria
    Ujene, Anthony Okwogume
    Edike, Uche Emmanuel
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2015, 15 (01) : 71 - 81