Automated trade-off between time and cost in planning repetitive construction projects

被引:47
作者
Hyari, Khalied Hesham [1 ]
El-Rayes, Khaled [2 ]
El-Mashaleh, Mohammad [1 ]
机构
[1] Hashemite Univ, Dept Civil Engn, Zarqa 13115, Jordan
[2] Univ Illinois, Civil & Environm Engn, Urbana, IL USA
关键词
Repetitive construction; scheduling; genetic algorithms; optimization; resource utilization;
D O I
10.1080/01446190903117793
中图分类号
F [经济];
学科分类号
02 ;
摘要
An automated model is developed to support the optimization of the planning and scheduling of repetitive construction projects. The model provides the capability of optimizing two important objectives commonly sought in scheduling repetitive construction projects: minimizing project duration; and minimizing project cost. The model performs this multi-objective optimization using a genetic algorithm approach. The output of the model is a set of optimal solutions that represent the trade-off between time and cost in planning repetitive construction projects. Furthermore, the model can be utilized to find a single scheduling solution that provides the minimum overall project cost by simply adding project indirect cost to the obtained project direct cost for each of the obtained scheduling solutions on the Pareto optimal curve. Other important time-related costs are also considered in the model including: early completion incentives, late completion penalties and lane rental costs. Providing the planners of repetitive construction projects with an automated set of optimal time-cost trade-off solutions should contribute to cost-effective and speedy delivery of this type of construction project. An application example is analysed to illustrate the use of the model and demonstrate its capabilities in generating optimal trade-off solutions between minimizing the project time and cost for repetitive construction projects.
引用
收藏
页码:749 / 761
页数:13
相关论文
共 36 条
[1]   Scheduling cost optimization and neural dynamics model for construction [J].
Adeli, H ;
Karim, A .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1997, 123 (04) :450-458
[2]  
Deb K., 2000, Parallel Problem Solving from Nature PPSN VI. 6th International Conference. Proceedings (Lecture Notes in Computer Science Vol.1917), P849
[3]  
El-Gafy M., 2006, P JOINT INT C CONSTR, P128
[4]   Optimum planning of highway construction under A+B bidding method [J].
El-Rayes, K .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (04) :261-269
[5]   Optimizing resource utilization for repetitive construction projects [J].
El-Rayes, K ;
Moselhi, O .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (01) :18-27
[6]  
El-Rayes K., 1998, CONSTR MANAG ECON, V16, P433
[7]   Object-oriented scheduling for repetitive projects with soft logics [J].
Fan, SL ;
Tserng, HP .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2006, 132 (01) :35-48
[8]   Stochastic construction time-cost trade-off analysis [J].
Feng, CW ;
Liu, L ;
Burns, SA .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2000, 14 (02) :117-126
[9]   Using genetic algorithms to solve construction time-cost trade-off problems [J].
Feng, CW ;
Liu, LA ;
Burns, SA .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) :184-189
[10]   Evolutionary resource scheduler for linear projects [J].
Georgy, Maged E. .
AUTOMATION IN CONSTRUCTION, 2008, 17 (05) :573-583