A HEURISTIC METHOD FOR THE ESTIMATION OF THE PROJECT DURATION IN A STOCHASTIC NETWORK SCHEDULING

被引:0
|
作者
GARAVELLI, AC [1 ]
PONTRANDOLFO, P [1 ]
机构
[1] POLITECN BARI,DPPI,I-70126 BARI,ITALY
来源
RAIRO-RECHERCHE OPERATIONNELLE-OPERATIONS RESEARCH | 1995年 / 29卷 / 03期
关键词
PROJECT MANAGEMENT; SCHEDULING; PERT;
D O I
暂无
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
In engineering and construction projects, the estimation of the completion date is often a complex task, When the uncertainty concerning project activity durations and the complexity of the project are not negligible, stochastic network techniques are more suitable to gain a reliable appraisal of the completion date. Since in these cases the conventional PERT computation can be inaccurate and the simulation can be too onerous, a heuristic method aimed to obtain fast and reliable results is proposed. An example of application of the heuristics to a real case of project scheduling is provided to show the heuristic implementation and effectiveness.
引用
收藏
页码:285 / 298
页数:14
相关论文
共 50 条
  • [1] Project scheduling problem with stochastic activity duration times
    Ke, Hua
    Liu, Baoding
    Proceedings of the Third International Conference on Information and Management Sciences, 2004, 3 : 284 - 289
  • [2] Project scheduling problem with stochastic activity duration times
    Ke, H
    Liu, BD
    APPLIED MATHEMATICS AND COMPUTATION, 2005, 168 (01) : 342 - 353
  • [3] A HEURISTIC SCHEDULING ALGORITHM FOR IMPROVING THE DURATION AND NET PRESENT VALUE OF A PROJECT
    ULUSOY, G
    OZDAMAR, L
    INTERNATIONAL JOURNAL OF OPERATIONS & PRODUCTION MANAGEMENT, 1995, 15 (01) : 89 - &
  • [4] A heuristic scheduling algorithm for improving the duration and net present value of a project
    Ulusoy, G.
    Oezdamar, L.
    International Journal of Operations & Production Management, 15 (01):
  • [5] Heuristic Algorithm in Optimizing Stochastic Resource-Constrained Project Scheduling
    Guo, Fang Ming
    Ma, Li
    He, Min
    INTERNATIONAL JOINT CONFERENCE ON COMPUTATIONAL SCIENCES AND OPTIMIZATION, VOL 1, PROCEEDINGS, 2009, : 975 - +
  • [6] Project scheduling problem with stochastic resource-dependent activity duration
    Zhong, Chunjie
    Yu, Ying
    Jia, YunLang
    MECHANICAL ENGINEERING, MATERIALS AND ENERGY III, 2014, 483 : 607 - +
  • [7] A stochastic scheduling for distributed multi-project with multi-PR heuristic
    Liu D.
    Xu Z.
    Xu, Zhe (xuzhebuaa@163.com), 1600, Systems Engineering Society of China (41): : 3294 - 3303
  • [8] A heuristic scheduling method for a large scale distribution network
    Li, Bo
    Tang, Zhizhong
    Zhu, Lin
    Journal of Information and Computational Science, 2015, 12 (13): : 4983 - 4992
  • [9] A neural network based heuristic for resource-constrained project scheduling
    Shou, YY
    ADVANCES IN NEURAL NETWORKS - ISNN 2005, PT 1, PROCEEDINGS, 2005, 3496 : 794 - 799
  • [10] A Multi-PR Heuristic for Distributed Multi-Project Scheduling With Uncertain Duration
    Liu, Dongning
    Xu, Zhe
    IEEE ACCESS, 2020, 8 : 227780 - 227792