Multi-mode resource-constrained project scheduling problem with material ordering under bonus–penalty policies

被引:3
作者
Nima Zoraghi
Aria Shahsavar
Babak Abbasi
Vincent Van Peteghem
机构
[1] Islamic Azad University,Faculty of Industrial and Mechanical Engineering
[2] RMIT University,School of Business IT and Logistics
[3] EDHEC Business School,undefined
来源
TOP | 2017年 / 25卷
关键词
Project scheduling; Multi-mode resource-constrained ; Material ordering; Particle swarm optimization; Genetic algorithm; Simulated annealing; 90-02; 90B35; 90B05; 90C11;
D O I
暂无
中图分类号
学科分类号
摘要
This study emphasizes that project scheduling and material ordering (time and quantity of an order) must be considered simultaneously to minimize the total cost, as setting the material ordering decisions after the project scheduling phase leads to non-optimal solutions. Hence, this paper mathematically formulates the model for the multi-mode resource-constrained project scheduling with material ordering (MRCPSMO) problem. In order to be more realistic, bonus and penalty policies are included for the project. The objective function of the model consists of four elements: the material holding cost, the material ordering cost, the bonus paid by the client and the cost of delay in the project completion. Since MRCPSMO is NP-hard, the paper proposes three hybrid meta-heuristic algorithms called PSO-GA, GA-GA and SA-GA to obtain near-optimal solutions. In addition, the design of experiments and Taguchi method is used to tune the algorithms’ parameters. The proposed algorithms consist of two components: an outside search, in which the algorithm searches for the best schedule and mode assignment, and the inside search, which determines the time and quantity of orders of the nonrenewable resources. First, a comparison is made for each individual component with the exact or best solutions available in the literature. Then, a set of standard PROGEN test problems is solved by the proposed hybrid algorithms under fixed CPU time. The results reveal that the PSO-GA algorithm outperforms both GA-GA and SA-GA algorithms and provides good solutions in a reasonable time.
引用
收藏
页码:49 / 79
页数:30
相关论文
共 108 条
[1]  
Alcaraz J(2003)Solving the multi-mode resource-constrained project scheduling problem with genetic algorithms J Oper Res Soc 54 614-626
[2]  
Maroto C(1980)A formal set of algorithms for project scheduling with critical path method material requirements planning J Oper Manag 1 57-67
[3]  
Ruiz R(2002)How to distribute costs associated with a delayed project Ann Oper Res 109 159-174
[4]  
Aquilano NJ(1993)Heuristics for scheduling projects with resource restrictions and several resource-duration modes Int J Prod Res 31 2547-2558
[5]  
Smith DE(1996)A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes Euro J Oper Res 90 349-361
[6]  
Bergantinos G(2002)Two approaches to the problem of sharing delay costs in joint projects Ann Oper Res 109 359-374
[7]  
Sanchez E(2007)A project game for PERT networks Oper Res Lett 35 791-798
[8]  
Boctor FF(2008)A polynomial rule for the problem of sharing delay costs in PERT networks Comp Oper Res 35 2376-2387
[9]  
Boctor FF(1987)An optimal algorithm for the quantity discount problem J Oper Manag 7 165-177
[10]  
Branzei R(2011)Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers Euro J Oper Res 213 73-82