Analysis of Scheduling Schemes and Heuristic Rules Performance in Resource-Constrained Multiproject Scheduling

被引:22
|
作者
Antonio Lova
Pilar Tormos
机构
[1] Universidad Politécnica de Valencia,Department of Statistics and Operations Research
来源
Annals of Operations Research | 2001年 / 102卷
关键词
project management; multiproject scheduling; heuristic based on priority rules; resource allocation; project management software;
D O I
暂无
中图分类号
学科分类号
摘要
Frequently, the availability of resources assigned to a project is limited and not sufficient to execute all the concurrent activities. In this situation, decision making about their schedule is necessary. Many times this schedule supposes an increase in the project completion time. Additionally, companies commonly manage various projects simultaneously, sharing a pool of renewable resources. Given these resource constraints, we often can only apply heuristic methods to solve the scheduling problem. In this work the effect of the schedule generation schemes – serial or parallel – and priority rules – MINLFT, MINSLK, MAXTWK, SASP or FCFS – with two approaches – multi-project and single-project – are analysed. The time criteria considered are the mean project delay and the multiproject duration increase. Through an extensive computational study, results show that with the parallel scheduling generation scheme and the multi-project approach the project manager can obtain a good multiproject schedule with the time criterion selected: minimising mean project delay or minimising multiproject duration increase. New heuristics – based on priority rules with a two-phase approach – that outperform classical ones are proposed to minimise mean project delay with a multi-project approach. Finally, the best heuristics analysed are evaluated together with a representative sample of commercial project management software.
引用
收藏
页码:263 / 286
页数:23
相关论文
共 50 条
  • [21] Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling
    Rob Van Eynde
    Mario Vanhoucke
    Journal of Scheduling, 2020, 23 : 301 - 325
  • [22] A Hybrid Heuristic for a Two-Agent Multi-Skill Resource-Constrained Scheduling Problem
    Haroune, Meya
    Soukhal, Ameur
    Dhib, Cheikh
    Babou, Hafed Mohamed
    Neron, Emmanuel
    Nanne, Farouk Mohamedade
    INTERNATIONAL JOURNAL OF ADVANCED COMPUTER SCIENCE AND APPLICATIONS, 2022, 13 (05) : 915 - 928
  • [23] Balancing Time and Cost in Resource-Constrained Project Scheduling Using Meta-Heuristic Approach
    Hajivand, A. Taheri
    Shirini, K.
    Gharehveran, S. Samadi
    JOURNAL OF AGRICULTURAL MACHINERY, 2024, 14 (02) : 215 - 234
  • [24] Network decomposition techniques for resource-constrained project scheduling
    Sprecher, A
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2002, 53 (04) : 405 - 414
  • [25] A Neurogenetic approach for the resource-constrained project scheduling problem
    Agarwal, Anurag
    Colak, Selcuk
    Erenguc, Selcuk
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 44 - 50
  • [26] MILP Formulation for Resource-Constrained Project Scheduling Problems
    Kyriakidis, Thomas S.
    Kopanos, Georgios M.
    Georgiadis, Michael C.
    21ST EUROPEAN SYMPOSIUM ON COMPUTER AIDED PROCESS ENGINEERING, 2011, 29 : 880 - 884
  • [27] Resource-constrained repetitive project scheduling with soft logic
    Zou, Xin
    Rong, Zhuang
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2025, 32 (04) : 2397 - 2429
  • [28] HEURISTICS FOR SCHEDULING RESOURCE-CONSTRAINED PROJECTS IN MPM NETWORKS
    ZHAN, J
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1994, 76 (01) : 192 - 205
  • [29] An efficient hybrid algorithm for resource-constrained project scheduling
    Chen, Wang
    Shi, Yan-jun
    Teng, Hong-fei
    Lan, Xiao-ping
    Hu, Li-chen
    INFORMATION SCIENCES, 2010, 180 (06) : 1031 - 1039
  • [30] Comparing Schedule Generation Schemes in Resource-Constrained Project Scheduling Using Elitist Genetic Algorithm
    Kim, Jin-Lee
    Ellis, Ralph D., Jr.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2010, 136 (02) : 160 - 169