Solving the nuclear dismantling project scheduling problem by combining mixed-integer and constraint programming techniques and metaheuristics

被引:0
作者
Felix Hübner
Patrick Gerhards
Christian Stürck
Rebekka Volk
机构
[1] Karlsruhe Institute of Technology (KIT),Institute for Industrial Production (IIP)
[2] Helmut Schmidt University,Institute of Computer Science
[3] Helmut Schmidt University,Institute for Management Science and Operations Research
来源
Journal of Scheduling | 2021年 / 24卷
关键词
Project scheduling; Multi-mode resource investment problem; Mixed-integer programming; Constraint programming; Metaheuristic; Nuclear dismantling project scheduling problem;
D O I
暂无
中图分类号
学科分类号
摘要
Scheduling of megaprojects is very challenging because of typical characteristics, such as expected long project durations, many activities with multiple modes, scarce resources, and investment decisions. Furthermore, each megaproject has additional specific characteristics to be considered. Since the number of nuclear dismantling projects is expected to increase considerably worldwide in the coming decades, we use this type of megaproject as an application case in this paper. Therefore, we consider the specific characteristics of constrained renewable and non-renewable resources, multiple modes, precedence relations with and without no-wait condition, and a cost minimisation objective. To reliably plan at minimum costs considering all relevant characteristics, scheduling methods can be applied. But the extensive literature review conducted did not reveal a scheduling method considering the special characteristics of nuclear dismantling projects. Consequently, we introduce a novel scheduling problem referred to as the nuclear dismantling project scheduling problem. Furthermore, we developed and implemented an effective metaheuristic to obtain feasible schedules for projects with about 300 activities. We tested our approach with real-life data of three different nuclear dismantling projects in Germany. On average, it took less than a second to find an initial feasible solution for our samples. This solution could be further improved using metaheuristic procedures and exact optimisation techniques such as mixed-integer programming and constraint programming. The computational study shows that utilising exact optimisation techniques is beneficial compared to standard metaheuristics. The main result is the development of an initial solution finding procedure and an adaptive large neighbourhood search with iterative destroy and recreate operations that is competitive with state-of-the-art methods of related problems. The described problem and findings can be transferred to other megaprojects.
引用
收藏
页码:269 / 290
页数:21
相关论文
共 65 条
[1]  
Alba E(2007)Software project management with GAs Information Sciences 177 2380-2401
[2]  
Chicano JF(1998)A branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations European Journal of Operational Research 111 152-174
[3]  
De Reyck B(2014)What you should know about megaprojects and why: An overview Project Management Journal 45 6-19
[4]  
Herroelen W(2017)A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem European Journal of Operational Research 256 729-741
[5]  
Flyvbjerg B(2017)An adaptive large neighborhood search as a matheuristic for the multi-mode resource-constrained project scheduling problem European Journal of Industrial Engineering 11 774-791
[6]  
Geiger MJ(2005)Project scheduling under uncertainty: Survey and research potentials European Journal of Operational Research 165 289-306
[7]  
Gerhards P(2005)A new heuristic for the multi-mode resource investment problem Journal of the Operational Research Society 56 406-413
[8]  
Stürck C(2004)Development of Decommissioning Engineering Support System (DEXUS) of the Fugen Nuclear Power Station Journal of Nuclear Science and Technology 41 367-375
[9]  
Fink A(2001)Simulated annealing for multi-mode resource-constrained project scheduling Annals of Operations Research 102 137-155
[10]  
Herroelen W(1963)The critical-path method: Resources planning and scheduling Industrial Scheduling 13 347-365