1000 MW ultra-supercritical turbine steam parameter optimization

被引:0
|
作者
Feng W. [1 ]
机构
[1] Shanghai Waigaoqiao No. 3 Power Generation Co. Ltd.
来源
Frontiers of Energy and Power Engineering in China | 2008年 / 2卷 / 2期
关键词
Parameter optimization; Sliding pressure operation; The overload valve; Turbine; Ultra-supercritical;
D O I
10.1007/s11708-008-0030-5
中图分类号
学科分类号
摘要
The 2×1000 MW ultra-supercritical steam turbine of Shanghai Waigaoqiao Phase III project, which uses grid frequency regulation and overload control through an overload valve, is manufactured by Shanghai Turbine Company using Siemens technology. Through optimization, the steam pressure is regarded as the criterion between constant pressure and sliding pressure operation. At high circulating water temperature, the turbine overload valve is kept closed when the unit load is lower than 1000 MW while at other circulating water temperatures the turbine can run in sliding pressure operation when the unit load is higher than 1000 MW and the pressure is lower than 27 MPa This increases the unit operation efficiency. The 3D bending technology in the critical piping helps to reduce the project investment and minimize the reheat system pressure drop which improves the unit operation efficiency and safety. By choosing lower circulating water design temperature and by setting the individual Boiler Feedwater Turbine condenser to reduce the exhaust steam flow and the heat load to the main condenser, the unit average back pressure and the terminal temperature difference are minimized. Therefore, the unit heat efficiency is increased. © 2008 Higher Education Press and Springer-Verlag GmbH.
引用
收藏
页码:187 / 193
页数:6
相关论文
共 50 条
  • [1] APPLICATION OF A CREEP DAMAGE CONSTITUTIVE MODEL FOR THE ROTOR OF A 1000 MW ULTRA-SUPERCRITICAL STEAM TURBINE
    Jiang, Jishen
    Wang, Weizhe
    Zhao, Nailong
    Wang, Peng
    Liu, Yingzheng
    Jiang, Puning
    PROCEEDINGS OF THE ASME TURBO EXPO: TURBINE TECHNICAL CONFERENCE AND EXPOSITION, 2015, VOL 8, 2015,
  • [2] Temperature at intermediate points of 1000 MW ultra-supercritical boilers and their steam temperature control
    Fan, Quan-Gui
    Dongli Gongcheng/Power Engineering, 2007, 27 (03): : 332 - 335
  • [3] RESEARCH AND DESIGN OF 1000 MW ULTRA-SUPERCRITICAL UNIT BOILER FEED PUMP TURBINE
    Zhang, Yuanlin
    Pan, Jiacheng
    Zhang, Jian
    Zhang, Qiong
    PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON POWER ENGINEERING 2009 (ICOPE-09), VOL 3, 2009, : 359 - 364
  • [4] Exergy analysis of the turbine system in a 1000 MW double reheat ultra-supercritical power plant
    Zhao, Zhigang
    Su, Sheng
    Si, Ningning
    Hu, Song
    Wang, Yi
    Xu, Jun
    Jiang, Long
    Chen, Gang
    Xiang, Jun
    ENERGY, 2017, 119 : 540 - 548
  • [6] Modeling and Simulation of Condenser for a 1000 MW Ultra-Supercritical Unit
    Wan, Xiang
    Huo, Min
    Hu, Nian-Su
    Zhang, Jiang-Hong
    INTERNATIONAL CONFERENCE ON FRONTIERS OF ENERGY, ENVIRONMENTAL MATERIALS AND CIVIL ENGINEERING (FEEMCE 2013), 2013, : 380 - 385
  • [7] A STUDY ON SUPERHEAT UTILIZATION OF EXTRACTION STEAM IN A 1000MW DOUBLE REHEAT ULTRA-SUPERCRITICAL UNIT
    Wang, Weiliang
    Zhang, Hai
    Lv, Junfu
    Ni, Weidou
    Li, Yongsheng
    Liu, Jianmin
    PROCEEDINGS OF THE ASME POWER CONFERENCE, 2016, 2016,
  • [8] Optimization of the Cold-end System of the 1000MW Ultra-supercritical Units by VB
    Zheng, Likun
    Chen, Chang
    Xie, Danmei
    Zhang, Hengliang
    MANUFACTURING PROCESS AND EQUIPMENT, PTS 1-4, 2013, 694-697 : 778 - +
  • [9] Fault diagnosis for steam-flow exciting vibration of ultra supercritical 1000MW steam turbine
    20160601888645
    Li, Chen, 2015, Bentham Science Publishers B.V., P.O. Box 294, Bussum, 1400 AG, Netherlands (09):
  • [10] STEAM FLOW AND HEAT TRANSFER IN THE INTERMEDIATE PRESSURE CYLINDER OF THE ULTRA-SUPERCRITICAL STEAM TURBINE
    Sun, Chong
    Zhou, Daiwei
    Zhu, Xiaocheng
    Du, Zhaohui
    PROCEEDINGS OF THE ASME TURBO EXPO: TURBOMACHINERY TECHNICAL CONFERENCE AND EXPOSITION, 2018, VOL 8, 2018,