The two-stage assembly flowshop scheduling problem with bicriteria of makespan and mean completion time

被引:0
|
作者
Ali Allahverdi
Fawaz S. Al-Anzi
机构
[1] Kuwait University,Department of Industrial and Management Systems Engineering
[2] Kuwait University,Department of Computer Engineering
来源
The International Journal of Advanced Manufacturing Technology | 2008年 / 37卷
关键词
Assembly flowshop; Bicriteria; Makespan; Mean competition time; Heuristic;
D O I
暂无
中图分类号
学科分类号
摘要
In this paper, we address the two-stage assembly flowshop scheduling problem with a weighted sum of makespan and mean completion time criteria, known as bicriteria. Since the problem is NP-hard, we propose heuristics to solve the problem. Specifically, we propose three heuristics; simulated annealing (SA), ant colony optimization (ACO), and self-adaptive differential evolution (SDE). We have conducted computational experiments to compare the performance of the proposed heuristics. It is statistically shown that both SA and SDE perform better than ACO. Moreover, the experiments reveal that SA, in general, performs better than SDE, while SA consumes less CPU time than both SDE and ACO. Therefore, SA is shown to be the best heuristic for the problem.
引用
收藏
页码:166 / 177
页数:11
相关论文
共 50 条
  • [21] A discrete PSO for two-stage assembly scheduling problem
    Tian, Ye
    Liu, Dayou
    Yuan, Donghui
    Wang, Kunhao
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 66 (1-4) : 481 - 499
  • [22] A grasp algorithm for m-machine flowshop scheduling problem with bicriteria of makespan and maximum tardiness
    Khan, B. Shahul Hamid
    Prabhaharan, G.
    Asokan, P.
    INTERNATIONAL JOURNAL OF COMPUTER MATHEMATICS, 2007, 84 (12) : 1731 - 1741
  • [23] The 2-stage assembly flowshop scheduling problem with total completion time: Efficient constructive heuristic and metaheuristic
    Framinan, Jose M.
    Perez-Gonzalez, Paz
    COMPUTERS & OPERATIONS RESEARCH, 2017, 88 : 237 - 246
  • [24] The two stage assembly flowshop scheduling problem to minimize total tardiness
    Ali Allahverdi
    Harun Aydilek
    Journal of Intelligent Manufacturing, 2015, 26 : 225 - 237
  • [25] A two-stage hybrid flowshop scheduling problem in machine breakdown condition
    Mirabi, M.
    Ghomi, S. M. T. Fatemi
    Jolai, F.
    JOURNAL OF INTELLIGENT MANUFACTURING, 2013, 24 (01) : 193 - 199
  • [26] Two-stage assembly scheduling problem for minimizing total tardiness with setup times
    Allahverdi, Ali
    Aydilek, Harlin
    Aydilek, Asiye
    APPLIED MATHEMATICAL MODELLING, 2016, 40 (17-18) : 7796 - 7815
  • [27] A bicriteria flowshop scheduling problem with setup times
    Eren, Tamer
    Guner, Ertan
    APPLIED MATHEMATICS AND COMPUTATION, 2006, 183 (02) : 1292 - 1300
  • [28] Bicriteria scheduling concerned with makespan and total completion time subject to machine availability constraints
    Huo, Yumei
    Zhao, Hairong
    THEORETICAL COMPUTER SCIENCE, 2011, 412 (12-14) : 1081 - 1091
  • [29] Memetic social spider optimization algorithm for scheduling two-stage assembly flowshop in a distributed environment
    Zhang, Guanghui
    Xing, Keyi
    COMPUTERS & INDUSTRIAL ENGINEERING, 2018, 125 : 423 - 433
  • [30] Cloud theory-based simulated annealing approach for scheduling in the two-stage assembly flowshop
    Torabzadeh, E.
    Zandieh, M.
    ADVANCES IN ENGINEERING SOFTWARE, 2010, 41 (10-11) : 1238 - 1243