Application of Axiomatic Design and Design Structure Matrix for Early Identification of Changes in Construction Projects

被引:0
作者
Padala S.P.S. [1 ]
机构
[1] Department of Civil Engineering, M. S. Ramaiah University of Applied Sciences, Karnataka, Bangalore
关键词
Axiomatic design; Change identification; Change management; Design structure matrix;
D O I
10.1007/s40030-021-00612-2
中图分类号
学科分类号
摘要
Changes are inevitable in construction projects. The primary cause of these changes includes inadequate requirements briefing, interdependencies, iterative loops, inadequate knowledge of construction methods, and the delayed inputs of information from interface teams. Parameters play an essential role in change communication. They are not only related to design but also depict and guide design processes. Changes can be better understood through modeling parameters relationships. Axiomatic Design (AD) and Design Structure Matrix (DSM) are two popular matrix-based modeling concepts that can model changes from a parameter perspective. AD guides the designers to examine changes by modeling requirements and parameters relationships in a structured manner from early design stages. DSM provides a methodology for analyzing changes through modeling interactions among the parameters. In spite of potential benefits of matrix-based approaches, previous studies have not dealt with combining AD and DSM for project change management research. Thus, the objective of this study is to conduct an in-depth investigation of these matrix-based design concepts to understand their applicability for better control on changes in construction projects. To achieve this objective, this study utilized a case study research method and data are collected from the ongoing metro underground project. A plant room design change case is taken up for illustration of the proposed framework. The novelty and unique contribution of this research work is development of AD-DSM framework to identify changes and its propagations due to functional and information couplings at conceptual design phase of construction projects. Changes that arises at later stages of project can be avoided and negative impacts can be minimized. The present study models the relationship of design parameters for accurate identification of changes. Changes can be tracked and scheduled early to minimize errors during implementation. © 2022, The Institution of Engineers (India).
引用
收藏
页码:647 / 661
页数:14
相关论文
共 31 条
  • [1] Wu C.H., Hsieh T.Y., Cheng W.L., Lu S.T., Grey relation analysis of causes for change orders in highway construction, Constr Manage Econ., 22, 5, pp. 509-520, (2004)
  • [2] Sun M., Meng X., Taxonomy for change causes and effects in construction projects, Int J Proj Manage, 27, pp. 560-572, (2009)
  • [3] Chua D.K.H., Hossain M.A., Predicting change propagation and impact on design schedule due to external changes, IEEE Trans Eng Manage., 59, pp. 483-493, (2012)
  • [4] Rachid Z., Toufik B., Mohammed B., Causes of schedule delays in construction projects in Algeria, Int J Constr Manage, 19, pp. 371-381, (2019)
  • [5] Yap J.B.H., Skitmore M., Gray J., Shavarebi K., Systemic View to Understanding Design Change Causation and Exploitation of Communications and Knowledge, Proj Manage J, 50, pp. 288-305, (2019)
  • [6] Padala S.P.S., Maheswari J.U., Hirani H., Identification and classification of changes causes and effects in construction projects, Int Constr Manage, (2020)
  • [7] Sanni-Anibire M.O., Mohamad Z.R., Olatunji S.O., Causes of delay in the global construction industry: A Meta Analytical Review, Int Constr Manage, pp. 1-13, (2020)
  • [8] Mittal Y.K., Paul V.K., Sawhney A., Methodology for Estimating the Cost of Delay in Architectural Engineering Projects: Case of Metro Rails in India, J. Inst. Eng. India Ser. A, 100, pp. 311-318, (2019)
  • [9] Singh M., Sarkar D., Vara D., Comparative Study of Risk Indices for Infrastructure Transportation Project Using Different Methods, J. Inst. Eng. India Ser. A, 100, pp. 275-286, (2019)
  • [10] Elkalla I., Elbeltagi E., El Shikh M., Solving Fuzzy Time-Cost Trade-Off in Construction Projects Using Linear Programming, J. Inst. Eng. India Ser. A, (2020)