Reliability-Centered Maintenance Strategy for Redundant Power Networks Using the Cut Set Method

被引:0
作者
Ji Woo Lee
Seung Wan Kim
机构
[1] Chungnam National University,Department of Electrical Engineering
来源
Journal of Electrical Engineering & Technology | 2022年 / 17卷
关键词
Cut set method; Dynamic programming; Redundant network; Reliability-centered maintenance; Semi-Markov chain;
D O I
暂无
中图分类号
学科分类号
摘要
In this study, we present an efficient maintenance strategy for securing stable power supplies in power facilities. In general, industrial customers that may face large outage costs from power supply interruptions prepare highly reliable systems with redundant network topologies. When establishing a maintenance schedule for an industrial power system, the condition of the equipment should be inspected first. However, frequent inspections may result in excessive inspection costs, and infrequent inspections may reduce the reliability of the system. Therefore, it is necessary to determine an optimal maintenance and inspection interval that balances the demand for reliable electricity and the need to limit maintenance and inspection costs. Accordingly, considering the topology of the equipment in terms of the system as a whole, a reliability-centered maintenance algorithm was derived to determine the specific combinations of equipment conditions that cause power outages. Generally, the more redundant the elements in the system were, the less the load experienced power outages. We also examined the unavailability, which is an indicator that predicts the probability of the load becoming unpowered. Finally, we obtained an optimal inspection interval and maintenance decision table for events that occur in practice.
引用
收藏
页码:1615 / 1621
页数:6
相关论文
共 29 条
[1]  
Arya R(2016)Ranking of feeder sections of distribution systems for maintenance prioritization accounting distributed generations and loads using diagnostic importance factor (DIF) Int J Electr Power Energy Syst 74 70-77
[2]  
Mirsaeedi H(2017)Electricity distribution system maintenance budgeting: a reliability-centered approach IEEE Trans Power Deliv 33 1599-1610
[3]  
Fereidunian A(2012)Application of particle swarm optimization to the reliability centered maintenance method for transmission systems J Electr Eng Technol 7 814-823
[4]  
Mohammadi-Hosseininejad SM(2014)Maintenance priority index of overhead transmission lines for reliability centered approach J Electr Eng Technol 9 1248-1257
[5]  
Lesani H(2011)Generalized reliability centered maintenance modeling through modified semi-Markov chain in power system J Electr Eng Technol 6 25-31
[6]  
Heo JH(1976)An efficient algorithm for deducing the minimal cuts and reliability indices of a general network configuration IEEE Trans Reliab 25 226-233
[7]  
Lyu JK(2012)Reliability model of the power transformer with ONAF cooling Int J Electr Power Energy Syst 35 97-104
[8]  
Kim MK(2015)Incorporating a condition monitoring based aging failure model of a circuit breaker in substation reliability assessment IEEE Trans Power Syst 30 3407-3415
[9]  
Park JK(undefined)undefined undefined undefined undefined-undefined
[10]  
Heo JH(undefined)undefined undefined undefined undefined-undefined