A robust scheduling of projects with time, cost, and quality considerations

被引:0
作者
Ali Salmasnia
Hadi Mokhtari
Isa Nakhai Kamal Abadi
机构
[1] Tarbiat Modares University,Department of Industrial Engineering, Faculty of Engineering
来源
The International Journal of Advanced Manufacturing Technology | 2012年 / 60卷
关键词
Project scheduling; Time, cost, and quality trade-off; Robust approach; Multi-response;
D O I
暂无
中图分类号
学科分类号
摘要
Quality is one of the main pillars that should be effectively considered in managing of industrial projects. In traditional project scheduling problems, only the time and cost are considered without the quality parameters. In this paper, it is suggested that the quality parameter is embedded into the traditional time–cost trade-off problem to develop a time, cost, and quality trade-off problem (TCQTP) with some practical assumptions. To the best of our knowledge, this problem has not been extensively treated in literature yet. The contributions of this article are in threefold: (1) incorporating a practical assumption to the TCQTP that is a relaxation of deterministic assumption to stochastic ones, which no paper has ever attempted to consider it in TCQTP; (2) relaxing the linearity assumption of time function, cost function, and quality function to a general form; and (3) integrating the TCQTP with a robust solution method to minimize the variation effect on time, cost, and quality. Computational experiments, which were done on benchmark problem, show the applicability and good performance of suggested TCQTP.
引用
收藏
页码:631 / 642
页数:11
相关论文
共 50 条
[41]   Collaborative supply chain planning and scheduling of construction projects [J].
Elmughrabi, Walid ;
Ben Sassi, Oumaima ;
Dao, Thien-My ;
Chabaane, Amin .
IFAC PAPERSONLINE, 2020, 53 (02) :10761-10766
[42]   Effectiveness and Efficiency of Scheduling Regional Water Resources Projects [J].
Chou, Frederick N-F ;
Lee, Hao-Chih ;
Yeh, William W-G .
WATER RESOURCES MANAGEMENT, 2013, 27 (03) :665-693
[43]   Scheduling tests in automotive R&D projects [J].
Bartels, J. -H. ;
Zimmermann, J. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2009, 193 (03) :805-819
[44]   A linear time-cost tradeoff problem with multiple interim assessments within multiple projects in parallel [J].
Choi, Byung-Cheon ;
Park, Myoung-Ju .
COMPUTERS & INDUSTRIAL ENGINEERING, 2019, 128 :651-658
[45]   Hybrid NSGA-III and simulated annealing approach for multi-objective time–cost-quality-sustainability optimization in wastewater treatment plant construction projects [J].
Vijay Kumar ;
Lilesh Gautam ;
Ritu Dahiya .
Asian Journal of Civil Engineering, 2025, 26 (6) :2569-2584
[46]   Safety plan modelling for resource-constrained construction projects to optimise cost, time, and safety risk [J].
Shafikhani, Ali Akbar ;
Pouyakian, Mostafa ;
Najafi, Amir Abbas ;
Afshar-Nadjafi, Behrouz ;
Kavousi, Amir .
INTERNATIONAL JOURNAL OF CRITICAL INFRASTRUCTURES, 2025, 21 (03) :228-251
[47]   Automatic Clustering and Multi-Directional Scheduling Scheme for Multi-Mode Scheduling Projects [J].
Yoosefzadeh, Hamid Reza .
INDUSTRIAL ENGINEERING AND MANAGEMENT SYSTEMS, 2019, 18 (03) :349-359
[48]   The Anchor-Robust Project Scheduling Problem [J].
Bendotti, Pascale ;
Chretienne, Philippe ;
Fouilhoux, Pierre ;
Pass-Lanneau, Adele .
OPERATIONS RESEARCH, 2023, 71 (06) :2267-2290
[49]   The resource-constrained time/cost trade-offs project scheduling with discount cash flow [J].
Zhang, JW ;
Xu, Y ;
He, ZW .
PROCEEDINGS OF THE 2005 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING (12TH), VOLS 1- 3, 2005, :2303-2307
[50]   A Multi-objective Genetic Algorithm for Optimization Time-Cost Trade-off Scheduling [J].
Aghassi, Hadi ;
Abadi, Sedigheh Nader ;
Roghanian, Emad .
KNOWLEDGE TECHNOLOGY, 2012, 295 :356-+