The optimal number of used machines in a two-stage flexible flowshop scheduling problem

被引:0
|
作者
Enrique Gerstl
Gur Mosheiov
机构
[1] The Hebrew University,School of Business Administration
来源
Journal of Scheduling | 2014年 / 17卷
关键词
Scheduling; Sequencing; Deterministic; Flowshop; Makespan; Flowtime;
D O I
暂无
中图分类号
学科分类号
摘要
We study practical scheduling problems with a major decision referring to the number of machines to be used. We focus on a two-stage flexible flowshop, where each job is processed on the first (critical) machine, and then continues to one of the second-stage parallel machines. Jobs are assumed to have identical processing times, and are processed in batches. A setup time is required when starting a new batch. We consider two objective functions: minimum makespan and minimum flowtime. In both cases, a closed form expression for the optimal number of machines to be used is introduced, and a unique and unusual sequence of decreasing batch sizes is shown to be optimal.
引用
收藏
页码:199 / 210
页数:11
相关论文
共 50 条
  • [11] TWO-STAGE FLOWSHOP SCHEDULING PROBLEMS WITH IDENTICAL AND BATCH PROCESSORS
    Wang Wen-Wei
    He Long-Min
    Cheng Ming-Bao
    ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2010, 27 (05) : 617 - 627
  • [12] Transfer batch scheduling for a two-stage flowshop with identical parallel machines at each stage
    Kim, JS
    Kang, SH
    Lee, SM
    OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1997, 25 (05): : 547 - 555
  • [13] Complexity and algorithms for two-stage flexible flowshop scheduling with availability constraints
    Xie, JX
    Wang, XJ
    COMPUTERS & MATHEMATICS WITH APPLICATIONS, 2005, 50 (10-12) : 1629 - 1638
  • [14] Scheduling a two-stage flowshop under makespan constraint
    Dawande, Milind
    Gavirneni, Srinagesh
    Rachamadugu, Ram
    MATHEMATICAL AND COMPUTER MODELLING, 2006, 44 (1-2) : 73 - 84
  • [15] TWO-STAGE ASSEMBLY FLOWSHOP SCHEDULING PROBLEM WITH MAXIMUM LATENESS AND MAKESPAN
    Allahverdi, All
    Al-Anzi, Fawaz S.
    PROCEEDINGS OF THE 38TH INTERNATIONAL CONFERENCE ON COMPUTERS AND INDUSTRIAL ENGINEERING, VOLS 1-3, 2008, : 2021 - 2028
  • [16] A two-stage hybrid flowshop scheduling problem in machine breakdown condition
    Mirabi, M.
    Ghomi, S. M. T. Fatemi
    Jolai, F.
    JOURNAL OF INTELLIGENT MANUFACTURING, 2013, 24 (01) : 193 - 199
  • [17] Fuzzy scheduling of job orders in a two-stage flowshop with batch-processing machines
    Yimer, Alebachew D.
    Demirli, Kudret
    INTERNATIONAL JOURNAL OF APPROXIMATE REASONING, 2009, 50 (01) : 117 - 137
  • [18] A note on two-stage hybrid flowshop scheduling with missing operations
    Tseng, Chao-Tang
    Liao, Ching-Jong
    Liao, Tai-Xiang
    COMPUTERS & INDUSTRIAL ENGINEERING, 2008, 54 (03) : 695 - 704
  • [19] A new heuristic for scheduling the two-stage flowshop with additional resources
    Figielska, Ewa
    COMPUTERS & INDUSTRIAL ENGINEERING, 2008, 54 (04) : 750 - 763
  • [20] Two algorithms for no-wait flexible flowshop scheduling problem with no-idle machines
    Jin, Qingwei
    Xing, Wenxun
    Proceedings of the Sixth International Conference on Information and Management Sciences, 2007, 6 : 636 - 640