Certification tests of the 215-MW power unit at the Pskov district power station for conformity with the standards under which the units of thermal power stations may participate in the standardized primary and automatic secondary control of frequency

被引:2
作者
Prytkov N.I. [1 ]
Fedorov V.V. [1 ]
Komarov K.V. [1 ]
Davydov N.I. [2 ]
Zorchenko N.V. [2 ]
Zhiganov M.A. [3 ]
机构
[1] Pskov District Power Station, OAO OGK-2, Dedovichi
[2] All-Russia Thermal Engineering Institute (VTI), Moscow 115280
[3] OAO ORGRES, Moscow 105023
关键词
Power Unit; Steam Superheater; Secondary Control; Power Assignment; Electric Power Output;
D O I
10.1134/S0040601507100011
中图分类号
学科分类号
摘要
We present the results of the certification tests of the station No. 1 power unit of the Pskov district power station that were carried out in October 2006 and aimed at checking if the unit complies with the requirements for the standardized primary and automatic secondary control of the frequency in a power system. © 2007 Pleiades Publishing, Inc.
引用
收藏
页码:763 / 768