Preventive Maintenance Prioritization by Fuzzy Logic for Seamless Hydro Power Generation

被引:3
作者
Roy P.K. [1 ]
Adhikary P. [2 ]
Mazumdar A. [1 ]
机构
[1] School of Water Resources Engineering, Jadavpur University, Kolkata
[2] Department of Mechanical Engineering, Swami Vivekananda Institute of Science and Technology (WBUT), Kolkata
关键词
Equipment breakdown; Fuzzy logic; Hydro power; Preventive maintenance;
D O I
10.1007/s40030-014-0076-9
中图分类号
学科分类号
摘要
Preventive maintenance prioritization is one of the most important criteria for the electricity generation planners to minimize the down time and production costs. Break down of equipments increases costs and plant down time results in loss of business. This work focuses on prioritizing the preventive maintenance for seamless hydro power generation considering (24 × 7) client’s power demand using fuzzy logic. The main task involves prioritizing the maintenance work considering constraints of varied power demand and hydro turbine plant breakdown. Fuzzy logic is used to optimize the preventive maintenance prioritization under the main constraints. Manual fuzzy arithmetic is used to develop the model and MATLAB Fuzzy Inference System editor used to validate the same. This novel fuzzy logic approach of preventive maintenance prioritizing for hydro power generation is absent in renewable power generation and industrial engineering literatures due to its assessment complexity. © 2014, The Institution of Engineers (India).
引用
收藏
页码:97 / 104
页数:7
相关论文
共 50 条
  • [1] Application of fuzzy logic control model to Gantt charting preventive maintenance scheduling
    Oke, S.
    Charles-Owaba, O.
    INTERNATIONAL JOURNAL OF QUALITY & RELIABILITY MANAGEMENT, 2006, 23 (04) : 441 - +
  • [2] Application of fuzzy logic control model to Gantt charting preventive maintenance scheduling
    Charles-Owaba, OE
    Oke, SA
    PROCEEDINGS OF THE 11TH INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1 AND 2: INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT IN THE GLOBAL ECONOMY, 2005, : 891 - 895
  • [3] Pavement rehabilitation and maintenance prioritization of urban roads using fuzzy logic
    Moazami, Danial
    Behbahani, Hamid
    Muniandy, Ratnasamy
    EXPERT SYSTEMS WITH APPLICATIONS, 2011, 38 (10) : 12869 - 12879
  • [4] Maintenance prioritization of interlocking concrete block pavement using fuzzy logic
    Gogoi R.
    Dutta B.
    Int. J. Pavement Res. Technol., 2020, 2 (168-175): : 168 - 175
  • [5] Fuzzy Logic Based Determination of Cost Overrun of Hydro Power Plant
    Shaktawat, Anuja
    Vadhera, Shelly
    2016 INTERNATIONAL CONFERENCE ON ELECTRICAL POWER AND ENERGY SYSTEMS (ICEPES), 2016, : 301 - 304
  • [6] An Automatic Frequency Controller for Kotmale Hydro Power Station using Fuzzy Logic
    Chaturanga, H. K. A.
    Samaliarachchi, Lalith A.
    Weerasinghe, M. Lakshitha
    ENGINEER-JOURNAL OF THE INSTITUTION OF ENGINEERS SRI LANKA, 2016, 49 (02): : 9 - 16
  • [7] Computational intelligence for preventive maintenance of power transformers
    Wong, Shen Yuong
    Ye, Xiaofeng
    Guo, Fengkai
    Goh, Hui Hwang
    APPLIED SOFT COMPUTING, 2022, 114
  • [8] Financial planning for the preventive maintenance of power distribution systems via fuzzy AHP
    Tehrani, Masood Khodaei
    Fereidunian, Alireza
    Lesani, Hamid
    COMPLEXITY, 2016, 21 (03) : 36 - 46
  • [9] Fuzzy adaptive preventive maintenance in a manufacturing control system: a step towards self-maintenance
    Yuniarto, MN
    Labib, AW
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2006, 44 (01) : 159 - 180
  • [10] Prioritization of maintenance tasks on industrial equipment for reliability: A fuzzy approach
    Kumar, Edwin
    Chaturvedi, S.
    INTERNATIONAL JOURNAL OF QUALITY & RELIABILITY MANAGEMENT, 2011, 28 (01) : 109 - +