Assessment of Risk Impact on Road Project Using Deep Neural Network

被引:0
作者
Muritala Adebayo Isah
Byung-Soo Kim
机构
[1] Kyungpook National University,Dept. of Civil Engineering
来源
KSCE Journal of Civil Engineering | 2022年 / 26卷
关键词
Risk impact; Artificial neural network; Deep neural network; Random forest regression; Schedule performance; Cost performance;
D O I
暂无
中图分类号
学科分类号
摘要
Road construction projects are complex endeavors, likewise the associated risks. Thus, identifying and assessing the potential risks associated with road projects is crucial to achieving project success. However, these associated risks are complex and dynamic, and the traditional risk assessment methods cannot accurately assess the risks. Hence, this paper presents a neural network approach by developing a deep neural network (DNN) model for assessing risk impact on project schedule and cost performance of road projects. The proposed DNN model was used to assess and predict the risk impact on 207 road projects in the Republic of Korea (ROK), and the accuracy was compared with a baseline neural network (BNN) and random forest regressor (RFR) models. The results show that the DNN model outperformed the BNN and RFR models, given the lowest mean squared error (MSE) and mean absolute error (MAE) values. The theoretical contribution of this study is related to risk assessment theory and the integration of expert judgment into a DNN model for effective risk assessment of road projects. Also, this study provides the practitioners with a systematic approach to predict accurate project schedule and cost performance considering the significant risk factors while enabling proper allocation of contingency allowance to schedule and cost baselines to guarantee project success.
引用
收藏
页码:1014 / 1023
页数:9
相关论文
共 96 条
[1]  
Al-Tabtabai H(2000)Modeling the cost of political risk in international construction projects Project Management Journal 31 4-13
[2]  
Alex AP(1999)Preliminary cost estimation of highway construction using neural networks Cost Engineering (Morgantown, West Virginia) 41 19-24
[3]  
Al-Tabtabai H(2020)A deep learning approach towards railway safety risk assessment IEEE Access 8 102811-102832
[4]  
Alex AP(2006)The importance and allocation of risks in Indonesian construction projects Construction Management and Economics 24 69-80
[5]  
Tantash M(2019)Fuzzy logic-based method for risk assessment of belt and road infrastructure projects Journal of Construction Engineering and Management 145 04019082-13
[6]  
Alawad H(2013)An evaluation of risk factors affecting performance of construction projects in Southwestern Nigeria PM World Journal II 1-383
[7]  
Member GS(2014)A review of risk management in construction: Opportunities for improvement Modern Economy 5 367-97
[8]  
Andi JM(2011)Construction risk modelling and assessment: Insights from a literature review Journal of the Built and Human Environment Review 4 87-66
[9]  
Andrić J(2004)Neural network model to support international market entry decisions Journal of Construction Engineering and Management 130 59-68
[10]  
Wang PXW(2006)An analytic hierarchy process based model for risk and opportunity assessment of international construction projects Canadian Journal of Civil Engineering 33 58-44