Comparison of Point Estimate and Monte Carlo probabilistic methods in stability analysis of a deep excavation

被引:7
作者
Sekhavatian A. [1 ]
Janalizadeh Choobbasti A. [1 ]
机构
[1] Department of Civil Engineering, Babol Noshirvani University of Technology, Babol
关键词
Excavation; Monte Carlo Simulation; Point Estimate Method; Probabilistic methods; Reliability analysis;
D O I
10.1186/s40703-018-0089-8
中图分类号
学科分类号
摘要
Geotechnical engineers have long used the lumped factor of safety approach in design of retaining walls. In recent years, uncertainty inherent in soil properties has caught more attentions from researchers, thus reliability analyses are used widely. In short, combining the probabilistic and deterministic analysis is common practice nowadays and failure probability calculated by risk analysis is a kind of complement of safety factor. In this paper, reliability analysis of a deep excavation is presented using two probabilistic methods called Point Estimate Method (PEM) and Monte Carlo Simulation (MCS) method. Horizontal displacement of the excavated wall, as well as safety of factor, are adopted as a basis for assessing the performance stability of the system. The paper explains why probabilistic analysis with numerical methods is challenging, and how PEM and MCS can be used to calculate the statistical moments of output variables and to estimate probability of failure. The results are presented and compared in terms of statistical moments, probability of occurrence and most likely values at every stage of construction. © 2018, The Author(s).
引用
收藏
相关论文
共 40 条
[1]  
Alonso E.E., Krizek R.J., Stochastic formulation of soil profiles, Proc Int Conf Appl Stat Probab (ICASP2), pp. 9-32, (1975)
[2]  
Babu G.L., Singh V.P., Reliability analysis of soil nail walls, J Georisk, 3, 1, pp. 44-54, (2009)
[3]  
Briaud J.L., Lim Y., Tieback walls in sand: numerical simulations and design implications, J Geotech Geoenviron Eng, 125, pp. 101-110, (1999)
[4]  
Carter J.P., Desai C.S., Potts D.M., Schweiger H.F., Sloan S.W., Computing and computer modeling in geotechnical engineering, Proc Geoeng 2000, Melbourne, Australia, 1, pp. 1157-1252, (2000)
[5]  
Chowdhury S.S., Reliability analysis of excavation induced basal heave, J Geotech Geol Eng, 35, 6, pp. 2705-2714, (2017)
[6]  
Chowdhury S.S., Deb K., Sengupta A., Effect of fines on behavior of braced excavation in sand: experimental and numerical study, Int J Geomech ASCE, (2016)
[7]  
Christian J.T., Baecher G.B., Point estimate method as numerical quadrature, J Geotech Geoenviron Eng (ASCE), 125, pp. 779-786, (1999)
[8]  
Christian J.T., Baecher G.B., The point-estimate method with large numbers of variables, Int J Numer Anal Meth Geomech, 26, pp. 1515-1529, (2002)
[9]  
Cornell C.A., First-order uncertainty analysis of soils deformation and stability, In: Proc Int Conf Appl Stat Probab (ICASP1), pp. 129-144, (1971)
[10]  
Duncan J.M., Factors of safety and reliability in geotechnical engineering, J Geotech Geoenviron Eng (ASCE), 126, pp. 307-316, (2000)