Investigating the challenges related to combining BIM and Last Planner System on construction sites

被引:0
作者
Conrad Boton
Yaya Pitti
Daniel Forgues
Ivanka Iordanova
机构
[1] École de Technologie Supérieure,Department of Construction Engineering
来源
Frontiers of Engineering Management | 2021年 / 8卷
关键词
Building Information Modeling; Last Planner System; construction site; lean construction;
D O I
暂无
中图分类号
学科分类号
摘要
The construction industry is facing a gradual but important transformation toward more productivity and collaboration. In this framework, two major approaches are often cited in the literature as having the potential to improve the practices in the industry: Building Information Modeling (BIM) and Lean Construction. Several scientific studies have demonstrated the synergy of these two approaches and very recent research has reported positive results from the use of software applications as support for their implementation on construction sites. However, the stakes of such integration have been very little studied. This article presents the results of a research project conducted within a general contractor firm that decided to implement BIM and Last Planner System (LPS) on its construction sites. The research uses a four-stage action research approach, including the characterization of the research issue, the establishment of an action plan, its implementation and its evaluation. Compared to recent related studies, the research is less enthusiastic. While it highlights the need for new tools to improve production planning and control, it also points to a strong resistance to change by practitioners at the site. They emphasize the necessity for adequate pre-service training and the need for new resources that can work full-time on the ongoing training of site teams. In addition, some limitations of the tool lead workers to believe that it can quickly become a factor that slows down their daily work rather than improving it. Based on the advice of professionals, the paper formulates some recommendations to the industry, the researchers and the software developers.
引用
收藏
页码:172 / 182
页数:10
相关论文
共 67 条
  • [1] AlSehaimi A O(2014)Improving construction management practice with the Last Planner System: A case study Engineering, Construction, and Architectural Management 21 51-64
  • [2] Tzortzopoulos Fazenda P(2011)BIM adoption and implementation for architectural practices Structural Survey 29 7-25
  • [3] Koskela L(2011)Technology adoption in the BIM implementation for lean architectural practice Automation in Construction 20 189-195
  • [4] Arayici Y(2004)Special issue on action research in information systems: Making IS research relevant to practice: Foreword Management Information Systems Quarterly 28 329-335
  • [5] Coates P(2011)Towards participatory action design research: Adapting action research and design science research methods for urban informatics Journal of Community Informatics 7 1-17
  • [6] Koskela L(2018)Practices and Processes in BIM Projects: An Exploratory Case Study Advances in Civil Engineering 2018 1-12
  • [7] Kagioglou M(2018)A framework for Building Information Modeling implementation in engineering education Canadian Journal of Civil Engineering 45 866-877
  • [8] Usher C(2013)Designing adapted visualization for collaborative 4D applications Automation in Construction 36 152-167
  • [9] O’Reilly K(2018)Comparison of shipbuilding and construction industries from the product structure standpoint International Journal of Product Lifecycle Management 11 191-220
  • [10] Arayici Y(1993)Improving business and information strategy alignment: Learning from the banking industry IBM Systems Journal 32 162-179