New fuzzy models for time-cost trade-off problem

被引:0
作者
Hua Ke
Weimin Ma
Xin Gao
Weihua Xu
机构
[1] Tongji University,School of Economics and Management
[2] North China Electric Power University,School of Mathematics and Physics
来源
Fuzzy Optimization and Decision Making | 2010年 / 9卷
关键词
Time-cost trade-off; Credibility theory; Fuzzy simulation; Genetic algorithm;
D O I
暂无
中图分类号
学科分类号
摘要
The time-cost trade-off problem is a specific type of the project scheduling problem which studies how to modify project activities so as to achieve the trade-off between the completion time and the project cost. In real projects, the trade-off between the project cost and the completion time, and the uncertainty of the environment are both considerable aspects for managers. In this paper, three new fuzzy time-cost trade-off models are proposed, in which credibility theory is applied to describe the uncertainty of activity duration times. A searching method by integrating fuzzy simulation and genetic algorithm is produced to search the quasi-optimal schedules under some decision-making criteria. The purpose of the paper is to reveal how to obtain the optimal balance of the completion time and the project cost in fuzzy environments.
引用
收藏
页码:219 / 231
页数:12
相关论文
共 84 条
  • [1] Azaron A.(2005)A genetic algorithm approach for the time-cost trade-off in PERT networks Applied Mathematics and Computation 168 1317-1339
  • [2] Perkgoz C.(1967)Dynamic programming for project cost-time curve Journal of Construction Division 93 59-73
  • [3] Sakawa M.(1981)The use of fuzzy variables in PERT Fuzzy Sets and Systems 5 11-19
  • [4] Butcher W. S.(1959)Chance-constrained programming Management Science 6 73-79
  • [5] Chanas S.(1962)A network interpretation and a direct sub-dual algorithm for critical path scheduling Journal of Industrial Engineering 13 213-219
  • [6] Kamburowski J.(1997)A time-cost trade-off model with resource consideration using genetic algorithm Civil Engineering Systems 14 291-311
  • [7] Charnes A.(2008)Time-cost optimization: Using GA and fuzzy sets theory for uncertainties in cost Construction Management and Economics 26 679-691
  • [8] Cooper W. W.(1997)Using genetic algorithms to solve construction time-cost trade-off problems Journal of Construction Engineering and Management 11 184-189
  • [9] Charnes A.(1960)A generalized network approach to project activity sequencing IRE Transactions on Engineering Management 7 103-107
  • [10] Cooper W. W.(2008)An application of possibility goal programming to the time-cost trade off problem Journal of Uncertain Systems 2 22-28