Application of CBO and CSS for Resource Allocation and Resource Leveling Problem

被引:0
|
作者
M. Khanzadi
A. Kaveh
M. Alipour
H. Karimi Aghmiuni
机构
[1] Iran University of Science and Technology,Centre of Excellence for Fundamental Studies in Structural Engineering, School of Civil Engineering
关键词
Resource allocation; Resource leveling problem; Metaheuristic algorithms; Colliding bodies optimization (CBO); Charged system search (CSS);
D O I
暂无
中图分类号
学科分类号
摘要
In construction projects, critical path method (CPM) has been mainly used for project scheduling and planning in the past. The main objective of CPM is to find critical activities and schedule the project in such a way that the project makespan is minimized. Resource allocation project scheduling problem has been one of the most popular issues among construction management researchers in the past decades. Resource leveling problem in the real world is also important and should be considered in the planning of a project. On the other side, since these two objectives have opposite goals in the projects, considering both of these objectives simultaneously has always been a challenging problem. In this paper, we try to solve these problems at the same time. For this purpose, two new metaheuristic algorithms so-called colliding body optimization and charged system search are utilized. Two case examples are solved to show the applicability and performance of the considered algorithms.
引用
收藏
页码:1 / 10
页数:9
相关论文
共 50 条
  • [1] Application of CBO and CSS for Resource Allocation and Resource Leveling Problem
    Khanzadi, M.
    Kaveh, A.
    Alipour, M.
    Aghmiuni, H. Karimi
    IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING, 2016, 40 (01) : 1 - 10
  • [2] Fuzzy Resource Constraint Project Scheduling Problem Using CBO and CSS Algorithms
    Kaveh, A.
    Khanzadi, M.
    Alipour, M.
    INTERNATIONAL JOURNAL OF CIVIL ENGINEERING, 2016, 14 (5A) : 325 - 337
  • [3] Fuzzy Resource Constraint Project Scheduling Problem Using CBO and CSS Algorithms
    A. Kaveh
    M. Khanzadi
    M. Alipour
    International Journal of Civil Engineering, 2016, 14 : 325 - 337
  • [4] CBO and CSS Algorithms for Resource Allocation and Time-Cost Trade-Off
    Kaveh, Ali
    Khanzadi, Mostafa
    Alipour, Majid
    Naraky, Mohammad Rajabi
    PERIODICA POLYTECHNICA-CIVIL ENGINEERING, 2015, 59 (03): : 361 - 371
  • [5] GA applied in project resource allocation and leveling scheduling problem
    Luo, SP
    Tang, XZ
    Lin, LF
    Progress in Intelligence Computation & Applications, 2005, : 703 - 708
  • [6] Uncertain resource leveling problem
    Ke, Hua
    Zhao, Chenkai
    JOURNAL OF INTELLIGENT & FUZZY SYSTEMS, 2017, 33 (04) : 2351 - 2361
  • [7] RESEARCH ON RESOURCE LEVELING PROBLEM UNDER RESOURCE CONSTRAINED CONDITION
    Wang, Qiang
    Qi, Jian-Xun
    PROCEEDINGS OF 2009 INTERNATIONAL CONFERENCE ON MACHINE LEARNING AND CYBERNETICS, VOLS 1-6, 2009, : 901 - 906
  • [8] A RESOURCE ALLOCATION PROBLEM
    LITSIOS, S
    OPERATIONS RESEARCH, 1965, S 13 : B71 - &
  • [9] A RESOURCE ALLOCATION PROBLEM
    LITSIOS, S
    OPERATIONS RESEARCH, 1965, 13 (06) : 960 - &
  • [10] Flexible resource-constrained resource leveling project scheduling problem
    Yu, Xiao-Guang
    Zhan, De-Chen
    Nie, Lan-Shun
    Chu, Dian-Hui
    Xu, Xiao-Fei
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2010, 16 (09): : 1967 - 1976