Mechanism for large-scale canyon deformations due to filling of large reservoir of hydropower project

被引:0
|
作者
Hui Jiang
Chu-Han Zhang
Yuan-De Zhou
Jian-Wen Pan
Jin-Ting Wang
Ming-Xin Wu
Qi-Xiang Fan
机构
[1] Tsinghua University,State Key Laboratory of Hydroscience and Engineering
[2] China Renewable Energy Engineering Institute,undefined
[3] China Three Gorges Corporation,undefined
[4] China Huaneng Group CO.,undefined
[5] LTD,undefined
来源
关键词
D O I
暂无
中图分类号
学科分类号
摘要
Large storage dam projects may modify geo-environmental conditions in many ways. The reservoir impoundment of the 285.5 m high Xiluodu arch dam located on the Jinsha River (China) caused large-scale canyon deformations, including significant canyon contraction and uplift movements from reservoir to downstream valley. The dam experienced subsequent tilting towards upstream and raised a safety concern of the project. A Thermo-Hydro-Mechanical (THM) mechanism is proposed for this extraordinary behavior. Due to reservoir impounding and seepage, significant temperature drops and fluid pressure increase within the underlying geothermal limestone aquifer in a synclinal basin are primary root causes. Finite element THM simulations successfully reproduce these unique deformations. Recent observations of large quantities of thermalized discharge water downstream and high pore pressure in the limestone layer provide further support for the proposed mechanism. Furthermore, refined numerical modeling is adopted to evaluate the safety of Xiluodu dam subjected to potential larger canyon contractions. We conclude that these unprecedented phenomena are dominantly the consequence of THM response to regional hydrogeological evolution following the build-up of a large reservoir. The accumulated canyon contractions at the current stage would not pose a direct threat to the dam safety, but a tripled situation may cause severe safety issues.
引用
收藏
相关论文
共 50 条
  • [1] Mechanism for large-scale canyon deformations due to filling of large reservoir of hydropower project
    Jiang, Hui
    Zhang, Chu-Han
    Zhou, Yuan-De
    Pan, Jian-Wen
    Wang, Jin-Ting
    Wu, Ming-Xin
    Fan, Qi-Xiang
    SCIENTIFIC REPORTS, 2020, 10 (01)
  • [2] Hydropower reservoir reoperation to adapt to large-scale photovoltaic power generation
    Ming, Bo
    Liu, Pan
    Guo, Shenglian
    Cheng, Lei
    Zhang, Jingwen
    ENERGY, 2019, 179 : 268 - 279
  • [3] LARGE-SCALE PROJECT
    MILI, M
    TELECOMMUNICATION JOURNAL, 1975, 42 (02): : 68 - 70
  • [4] Large-scale hydropower system optimization
    Barros, MTL
    Lopes, JEG
    Yang, SL
    Yeh, WWG
    INTEGRATED WATER RESOURCES MANAGEMENT, 2001, (272): : 263 - 268
  • [5] Scanning large-scale articulated deformations
    Lang, JC
    Pai, DK
    Seidel, HP
    GRAPHICS INTERFACE 2003, PROCEEDING, 2003, : 265 - 272
  • [6] Design of High Precision Horizontal Control Network for Large-Scale Hydropower Project
    Zhang Zhenglu
    Luo Changlin
    Deng Yong
    Xie Niansheng
    GEO-SPATIAL INFORMATION SCIENCE, 2006, 9 (04) : 235 - 239
  • [7] Design of High Precision Horizontal Control Network for Large-Scale Hydropower Project
    ZHANG Zhenglu LUO Changlin DENG Yong XIE Niansheng
    Geo-Spatial Information Science, 2006, (04) : 235 - 239
  • [8] Large Deformation Prediction and Feedback for A Reservoir Slope near A Large-scale Hydropower Station in the Upstream of Yellow River
    Peng, Jing
    Fu, Wenxi
    ADVANCES IN CIVIL ENGINEERING, PTS 1-4, 2011, 90-93 : 1684 - 1690
  • [9] Quarter-Hourly Operation of Large-Scale Hydropower Reservoir Systems with Prioritized Constraints
    Wang, Jinwen
    Liu, Shuangquan
    Zhang, Yongchuan
    JOURNAL OF WATER RESOURCES PLANNING AND MANAGEMENT, 2015, 141 (01)
  • [10] Optimization of large-scale hydropower system operations
    Barros, MTL
    Tsai, FTC
    Yang, SL
    Lopes, JEG
    Yeh, WWG
    JOURNAL OF WATER RESOURCES PLANNING AND MANAGEMENT, 2003, 129 (03) : 178 - 188