The just-in-time job-shop scheduling problem with distinct due-dates for operations

被引:0
|
作者
Mohammad Mahdi Ahmadian
Amir Salehipour
机构
[1] University of Technology Sydney,School of Mathematical and Physical Sciences
来源
Journal of Heuristics | 2021年 / 27卷
关键词
Just-in-time scheduling; Earliness and tardiness; Matheuristic; Heuristic; Variable neighborhood search; Relax-and-solve;
D O I
暂无
中图分类号
学科分类号
摘要
In the just-in-time job-shop scheduling (JIT–JSS) problem every operation has a distinct due-date, and earliness and tardiness penalties. Any deviation from the due-date incurs penalties. The objective of JIT–JSS is to obtain a schedule, i.e., the completion time for performing the operations, with the smallest total (weighted) earliness and tardiness penalties. This paper presents a matheuristic algorithm for the JIT–JSS problem, which operates by decomposing the problem into smaller sub-problems, optimizing the sub-problems and delivering the optimal schedule for the problem. By solving a set of 72 benchmark instances ranging from 10 to 20 jobs and 20 to 200 operations we show that the proposed algorithm outperforms the state-of-the-art methods and the solver CPLEX, and obtains new best solutions for nearly 56% of the instances, including for 79% of the large instances with 20 jobs.
引用
收藏
页码:175 / 204
页数:29
相关论文
共 50 条
  • [21] Cooperative games on proportionate flow-shop scheduling problem with due-dates
    Sun W.-J.
    Gong H.
    Xu K.
    Liu P.
    Kongzhi yu Juece/Control and Decision, 2022, 37 (03): : 712 - 720
  • [22] JOB-SHOP SCHEDULING WITH RESOURCE-TIME MODELS OF OPERATIONS
    GRABOWSKI, J
    JANIAK, A
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1987, 28 (01) : 58 - 73
  • [23] Just-in-time scheduling problem with due windows and release dates for precast bridge girders
    Liu, Gang
    Wang, Hongwei
    Xie, Yong
    INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2024, 31 (04) : 2366 - 2398
  • [24] THE EFFECT OF WORKLOAD DEPENDENT DUE-DATES ON JOB SHOP PERFORMANCE
    BERTRAND, JWM
    MANAGEMENT SCIENCE, 1983, 29 (07) : 799 - 816
  • [25] Integrated job release and shop-floor scheduling to minimize WIP and meet due-dates
    Zozom, A
    Hodgson, TJ
    King, RE
    Weintraub, AJ
    Cormier, D
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2003, 41 (01) : 31 - 45
  • [26] ANALYTICAL DETERMINATION OF OPTIMAL TWK DUE-DATES IN A JOB SHOP
    CHENG, TCE
    INTERNATIONAL JOURNAL OF SYSTEMS SCIENCE, 1985, 16 (06) : 777 - 787
  • [28] JOB-SHOP SCHEDULING WITH CONVEX MODELS OF OPERATIONS
    JANIAK, A
    SZKODNY, T
    MATHEMATICAL AND COMPUTER MODELLING, 1994, 20 (02) : 59 - 68
  • [29] OPTIMIZATION OF JUST-IN-TIME PART SUPPLY SCHEDULING IN ASSEMBLY JOB SHOP
    Sun, Lin
    Xiao, Feng
    2019 16TH INTERNATIONAL COMPUTER CONFERENCE ON WAVELET ACTIVE MEDIA TECHNOLOGY AND INFORMATION PROCESSING (ICWAMTIP), 2019, : 443 - 446
  • [30] Batch Scheduling Problem with Multiple Due-dates Constraints
    Mohri, Shintaro
    Masuda, Teruo
    Hiroakilshii
    INDUSTRIAL ENGINEERING AND MANAGEMENT SYSTEMS, 2011, 10 (01): : 1 - 6