A multi-objective algorithm for U-shaped disassembly line balancing with partial destructive mode

被引:1
作者
Kaipu Wang
Liang Gao
Xinyu Li
机构
[1] Huazhong University of Science and Technology,State Key Laboratory of Digital Manufacturing Equipment and Technology, School of Mechanical Science and Engineering
来源
Neural Computing and Applications | 2020年 / 32卷
关键词
Disassembly line balancing; Partial destructive disassembly; Multi-objective optimization; Flower pollination algorithm;
D O I
暂无
中图分类号
学科分类号
摘要
The disassembly line is the best way to deal with large-scale waste electrical and electronic equipment. Balancing of disassembly line is a hot and challenging problem in recent years. Given the uncertainty factors including corrosion and deformation of parts and components of waste products, this paper introduces the destructive mode and uncertainty disassembly time into the disassembly line and establishes a multi-objective disassembly line balancing model, considering partial destructive mode and U-shaped layout. The model aims to reduce the number of stations, balance the workload and reduce energy consumption while increasing the disassembly profit. A new multi-objective discrete flower pollination algorithm is proposed to solve the problem. Both task assignment and disassembly modes are considered in the encoding and decoding strategies of the flowers. Combining the discrete characteristics of the problem, the cross-pollination and self-pollination behaviors of the algorithm are redefined. The performance of the proposed algorithm is verified by solving two classical examples and by comparing with seven meta-heuristic algorithms. Then the proposed model and method are applied to a television disassembly line of a disassembly enterprise in China. The disassembly schemes of the proposed algorithm are superior to that of the five classical multi-objective algorithms. The results show that the proposed method can improve the performance of the disassembly line.
引用
收藏
页码:12715 / 12736
页数:21
相关论文
共 133 条
[1]  
Xia K(2016)Service-oriented disassembly sequence planning for electrical and electronic equipment waste Electron Commer Res Appl 20 59-68
[2]  
Gao L(2002)Disassembly line in product recovery Int J Prod Res 40 2569-2589
[3]  
Wang L(2001)A solution approach to the disassembly line balancing problem in the presence of task failures Int J Prod Res 39 1427-1467
[4]  
Li W(2007)A balancing method and genetic algorithm for disassembly line balancing Eur J Oper Res 179 692-708
[5]  
Li X(2019)Partial disassembly line balancing for energy consumption and profit under uncertainty Robot Comput-Integr Manuf 59 235-251
[6]  
Ijomah W(2018)Profit-oriented partial disassembly line design: dealing with hazardous parts and task processing times uncertainty Int J Prod Res 56 7220-7242
[7]  
Gungor A(2019)An extended review on disassembly line balancing with bibliometric & social network and future study realization analysis J Clean Prod 225 697-715
[8]  
Gupta SM(2014)Disassembly sequence planning for electro-mechanical products under a partial destructive mode Assem Autom 34 106-114
[9]  
Gungor A(2008)A collaborative ant colony algorithm to stochastic mixed-model U-shaped disassembly line balancing and sequencing problem Int J Prod Res 46 1405-1429
[10]  
Gupta SM(2019)A multi-objective discrete flower pollination algorithm for stochastic two-sided partial disassembly line balancing problem Comput Ind Eng 130 634-649