A mixed (continuous + discrete) time-cost trade-off model considering four different relationships with lag time

被引:0
|
作者
Jaeho Son
TaeHoon Hong
Sangyoub Lee
机构
[1] Hongik University,School of Architectural Engineering
[2] Yonsei University,Dept. of Architectural Engineering
[3] Konkuk University,Dept. of Real Estate Studies
来源
KSCE Journal of Civil Engineering | 2013年 / 17卷
关键词
Time-Cost Trade-Off; critical path method; optimization models; linear programming; integer programming; costs;
D O I
暂无
中图分类号
学科分类号
摘要
Numerous Time-Cost Trade-Off (TCTO) models have been developed to identify the best combination of time and cost in a critical path network. Although there are four relationships in the critical path network, most of the models developed so far have considered only the Finish-Start (F-S) relationship. Thus, an advanced TCTO model that considers all four relationships between activities was developed in this study to accurately present a project, and is presented in this paper. The model also takes into account the lag time between activities. Previous TCTO models minimize the total project cost based on the given crash scenario. Moreover, to enhance the practicality, the model was developed to work with various TCTO scenarios such as continuous, discrete, and even mixed (continuous + discrete). The combined scenario reflects the most realistic situation. Two independent scenarios cannot be combined without mathematical modifications since a rudimentary mixing of two scenarios may provide an incorrect solution. A new formulation technique is introduced to merge the two independent scenarios mathematically and it guarantees the optimal solution.
引用
收藏
页码:281 / 291
页数:10
相关论文
共 50 条
  • [41] A new approach to solve time-cost trade-off problem with fuzzy decision variables
    Ghazanfari, M.
    Yousefli, A.
    Ameli, M. S. Jabal
    Bozorgi-Amiri, A.
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 42 (3-4) : 408 - 414
  • [42] Application of time-cost trade-off model in forest management projects: The case of Oak decline project
    Zandebasiri, Mehdi
    Vacik, Harald
    Etongo, Daniel
    Dorfstetter, Yasmin
    Soosani, Javad
    Pourhashemi, Mehdi
    JOURNAL OF FOREST SCIENCE, 2019, 65 (12) : 481 - 492
  • [43] The discrete time/cost trade-off problem: extensions and heuristic procedures
    Mario Vanhoucke
    Dieter Debels
    Journal of Scheduling, 2007, 10 : 311 - 326
  • [44] Time-Cost Trade-off Problem in Construction Supply Chain: A Bi-level Programming Decision Model
    Chen Jian-hua
    Tang Wan
    2010 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE AND ENGINEERING (ICMSE), 2010, : 212 - 217
  • [45] A Bi-level Programming Decision Model for Time-Cost Trade-off Problem in Construction Supply Chain
    Chen, Si-yun
    Shen, Si-min
    Chen, Jian-hua
    ICOSCM 2009 - PROCEEDINGS OF THE 3RD INTERNATIONAL CONFERENCE ON OPERATIONS AND SUPPLY CHAIN MANAGEMENT, 2009, 3 : 354 - 359
  • [46] Multi-objective time-cost trade-off optimization for the construction scheduling with Rao algorithms
    Yilmaz, Mehmet
    Dede, Tayfun
    STRUCTURES, 2023, 48 : 798 - 808
  • [47] Time-Cost Trade-off Optimization of Construction Projects using Teaching Learning Based Optimization
    Vedat Toğan
    M. Azim Eirgash
    KSCE Journal of Civil Engineering, 2019, 23 : 10 - 20
  • [48] Optimization models and a GA-based algorithm for stochastic time-cost trade-off problem
    Ke, Hua
    Ma, Weimin
    Ni, Yaodong
    APPLIED MATHEMATICS AND COMPUTATION, 2009, 215 (01) : 308 - 313
  • [49] Robust Proactive Project Scheduling Model for the Stochastic Discrete Time/Cost Trade-Off Problem
    Li, Hongbo
    Xu, Zhe
    Xiong, Li
    Liu, Yinbin
    DISCRETE DYNAMICS IN NATURE AND SOCIETY, 2015, 2015
  • [50] Use of Support Vector Regression to Improve Computational Efficiency of Stochastic Time-Cost Trade-Off
    Yang, I-Tung
    Lin, Yu-Cheng
    Lee, Hsin-Yun
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (01)