A mixed (continuous + discrete) time-cost trade-off model considering four different relationships with lag time

被引:0
|
作者
Jaeho Son
TaeHoon Hong
Sangyoub Lee
机构
[1] Hongik University,School of Architectural Engineering
[2] Yonsei University,Dept. of Architectural Engineering
[3] Konkuk University,Dept. of Real Estate Studies
来源
KSCE Journal of Civil Engineering | 2013年 / 17卷
关键词
Time-Cost Trade-Off; critical path method; optimization models; linear programming; integer programming; costs;
D O I
暂无
中图分类号
学科分类号
摘要
Numerous Time-Cost Trade-Off (TCTO) models have been developed to identify the best combination of time and cost in a critical path network. Although there are four relationships in the critical path network, most of the models developed so far have considered only the Finish-Start (F-S) relationship. Thus, an advanced TCTO model that considers all four relationships between activities was developed in this study to accurately present a project, and is presented in this paper. The model also takes into account the lag time between activities. Previous TCTO models minimize the total project cost based on the given crash scenario. Moreover, to enhance the practicality, the model was developed to work with various TCTO scenarios such as continuous, discrete, and even mixed (continuous + discrete). The combined scenario reflects the most realistic situation. Two independent scenarios cannot be combined without mathematical modifications since a rudimentary mixing of two scenarios may provide an incorrect solution. A new formulation technique is introduced to merge the two independent scenarios mathematically and it guarantees the optimal solution.
引用
收藏
页码:281 / 291
页数:10
相关论文
共 50 条
  • [1] A mixed (continuous plus discrete) time-cost trade-off model considering four different relationships with lag time
    Son, Jaeho
    Hong, TaeHoon
    Lee, Sangyoub
    KSCE JOURNAL OF CIVIL ENGINEERING, 2013, 17 (02) : 281 - 291
  • [2] New Time-Cost Trade-Off Model Considering the Sequence of Alternatives Between Activities
    Kang, Namuk
    Son, Jaeho
    Lee, Seunghyun
    JOURNAL OF ASIAN ARCHITECTURE AND BUILDING ENGINEERING, 2015, 14 (02) : 379 - 386
  • [3] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [4] A crashing-based time-cost trade-off model considering quality cost and contract clauses
    Akin, Firat Dogu
    Polat, Gul
    Turkoglu, Harun
    Damci, Atilla
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2021, 23 (06) : 954 - 963
  • [5] Flexible Resource-constrained Discrete Time-cost Trade-off Problem Considering Resource Transfer
    Zou, Haobo
    Zhou, Guohua
    JOURNAL OF INTERNET TECHNOLOGY, 2021, 22 (01): : 197 - 207
  • [6] Network analysis algorithm for the solution of discrete time-cost trade-off problem
    Önder Halis Bettemir
    M. Talat Birgönül
    KSCE Journal of Civil Engineering, 2017, 21 : 1047 - 1058
  • [7] Network Analysis Algorithm for the Solution of Discrete Time-Cost Trade-off Problem
    Bettemir, Onder Halis
    Birgonul, M. Talat
    KSCE JOURNAL OF CIVIL ENGINEERING, 2017, 21 (04) : 1047 - 1058
  • [8] AN IMPROVED TIME-COST TRADE-OFF MODEL WITH OPTIMAL LABOR PRODUCTIVITY
    Lin, Chien-Liang
    Lai, Yu-Che
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2020, 26 (02) : 113 - 130
  • [9] Pareto Front Particle Swarm Optimizer for Discrete Time-Cost Trade-Off Problem
    Aminbakhsh, Saman
    Sonmez, Rifat
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (01)
  • [10] New fuzzy models for time-cost trade-off problem
    Hua Ke
    Weimin Ma
    Xin Gao
    Weihua Xu
    Fuzzy Optimization and Decision Making, 2010, 9 : 219 - 231