Seepage behavior of drainage zoning in a concrete faced gravel-fill dam via centrifuge and numerical modeling

被引:0
作者
Yun Wook Choo
Dong Hoon Shin
Sung Eun Cho
Eun Sang Im
Dong-Soo Kim
机构
[1] Korea Advanced Institute of Science and Technology (KAIST),Dept. of Civil and Environmental Engineering
[2] Korea Water Resources Corporation,K
[3] Hankyong National University,water Institute
来源
KSCE Journal of Civil Engineering | 2013年 / 17卷
关键词
concrete faced gravel-fill dam; centrifuge modeling; zoning; seepage; drainage zone;
D O I
暂无
中图分类号
学科分类号
摘要
Sandy gravel materials have recently been utilized in place of crushed rock materials as the main rockfill materials in Concrete Faced Rockfill Dams (CRFD) to address geological and environmental problems. In this paper, an experimental scheme for centrifuge modeling was developed to simulate a Concrete Faced Gravel-fill Dam (CFGD). The dam considered in this study was designed to implement a drainage zone of high permeability in the main gravel-fill zone to enhance safety against accidental water infiltration into the dam. Two centrifuge tests were performed and compared to investigate the performance of the drainage zone. The first test was done with the drainage zone and the second without the drainage zone. In the centrifuge tests, water infiltration was simulated by raising the water table over pre-implemented cracks on the model face slab. The infiltration behaviors were monitored by pore water pressure transducers. The centrifuge tests showed that the drainage zone of the CFGD effectively drains infiltrating water out of the dam body in a short time. Numerical modeling was also performed to help understand the process of seepage through cracks.
引用
收藏
页码:949 / 958
页数:9
相关论文
共 33 条
[1]  
Aubertin M(2003)A model to predict the water retention curve from basic geotechnical properties Canadian Geotechnical Journal 40 1104-1122
[2]  
Mbonimpa M(2006)Three-dimensional analysis of water infiltration into the Gouhou rockfill dam using saturatedunsaturated seepage theory Canadian Geotechnical Journal 43 449-461
[3]  
Bussière B(1984)Post-construction deformation of rockfill dams Journal of Geotechnical Engineering, ASCE 110 821-840
[4]  
Chapuis R P(1984)Progress in rockfill dams (18th Terzaghi Lecture) J. Geotechnical Engineering, ASCE 110 1381-1414
[5]  
Chen Q(1994)Predicting the permeability function for unsaturated soils using the soil-water characteristic curve Canadian Geotechnical Journal 31 533-546
[6]  
Zhang L M(2003)Rockfill modulus and settlement of concrete face rockfill dams Journal of Geotechnical and Geoenvironmental Engineering, ASCE 129 909-917
[7]  
Clements R P(2013)A newly developed state-of-the-art geotechnical centrifuge in korea KSCE Journal of Civil Engineering 17 77-84
[8]  
Cooke J B(2008)Very high CFRDs: Behaviour and design features International Journal on Hydropower and Dams 15 43-49
[9]  
Fredlund D G(1980)Cambridge university geotechnical centrifuge operation, Rankine lecture Geotechnique 30 227-268
[10]  
Xing A(2009)Behavior of concrete-faced rockfill dams during initial impoundment Journal of Geotechnical and Geoenvironmental Engineering, ASCE 135 1070-1081