Factors influencing Time and Cost Overruns on Freeform Construction Projects

被引:0
作者
Andrew Kavuma
Jongho Ock
Hyounseung Jang
机构
[1] Seoul National University of Science and Technology,School of Architecture
来源
KSCE Journal of Civil Engineering | 2019年 / 23卷
关键词
time overruns; cost overruns; freeform projects; Building Information Modeling (BIM); latent factors;
D O I
暂无
中图分类号
学科分类号
摘要
Freeform buildings differ from conventional buildings in a way that they have irregularly shaped facades. Oftentimes, freeform projects run behind schedule and over the budget. This study aimed at exploring factors that influence time and cost overruns on freeform buildings. The study employed questionnaire surveys to collect data from experts with freeform project experience, and the responses were analyzed using R statistical program. The study used exploratory factor analysis to identify the most critical latent factors to freeform project success. The study found factors related to application of Building Information Modeling (BIM) and fabrication of freeform components as very crucial to timely completion, whereas factors related to personnel involved as essential to completing within budget. Additionally, the study summarized time overrun variables into three latent factors; uniqueness, capabilities and practices of the parties involved, and level of preparation for the project. The cost overrun latent factors were: cost uncertainty, client decisions, extent of preparation, and delay. Understanding the causes of time and cost overruns on freeform buildings identified in this study can help clients make informed decisions regarding undertaking freeform projects as well as help consultants and contractors minimize the risk of encountering such overruns.
引用
收藏
页码:1442 / 1450
页数:8
相关论文
共 50 条
[41]   Causes, effects and solutions of delay and cost overruns in Iranian deep excavation projects [J].
Bayandor, Sara ;
Kalatehjari, Roohollah ;
Akherati, Reza ;
Kasebzadeh, Jalal .
BUILT ENVIRONMENT PROJECT AND ASSET MANAGEMENT, 2025, 15 (02) :309-336
[42]   Persisting Cost Overruns in Public Infrastructure Projects: Lessons From the Belgian Case [J].
Molinari, Laura ;
Haezendonck, Elvira ;
Van Rompay, Katrien ;
Mabillard, Vincent ;
Dooms, Michael .
PUBLIC WORKS MANAGEMENT & POLICY, 2025, 30 (01) :36-57
[43]   Cost Overruns and Formal Risk Assessment Program in US Rail Transit Projects [J].
Gao, Nan ;
Touran, Ali .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2020, 146 (05)
[44]   Structural model of cost overrun factors affecting Pakistani construction projects [J].
Memon, Aftab Hameed ;
Memon, Abdul Qadir ;
Memon, Muneeb Ayub ;
Sahito, Jam Shahzeb Khan .
MEHRAN UNIVERSITY RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY, 2023, 42 (02) :108-123
[45]   Using principal component analysis to identify latent factors affecting cost and time overrun in public construction projects [J].
Wyke, Simon ;
Lindhard, Soren Munch ;
Larsen, Jesper Kranker .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2023, 31 (06) :2415-2436
[46]   Cost Overruns in Large-scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness [J].
Cantarelli, Chantal C. ;
Flyvbjerg, Bent ;
Molin, Eric J. E. ;
van Wee, Bert .
EUROPEAN JOURNAL OF TRANSPORT AND INFRASTRUCTURE RESEARCH, 2010, 10 (01) :5-18
[47]   Integrated priority decision index for risk assessment in chaos: cost overruns in transport projects [J].
Afzal, Farman ;
Shao, Yunfei ;
Sajid, Muhammad ;
Afzal, Fahim .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2020, 27 (04) :825-849
[48]   Causes of cost overruns in transport infrastructure projects in Asia Their significance and relationship with project size [J].
Park, Young-Ill ;
Papadopoulou, Theopisti C. .
BUILT ENVIRONMENT PROJECT AND ASSET MANAGEMENT, 2012, 2 (02) :195-216
[49]   Assessment of cost overrun factors in construction projects in Nigeria using fuzzy logic [J].
Obianyo, Jude Iloabuchi ;
Okey, Okey Enangha ;
Alaneme, George Uwadiegwu .
INNOVATIVE INFRASTRUCTURE SOLUTIONS, 2022, 7 (05)
[50]   Assessment of cost overrun factors in construction projects in Nigeria using fuzzy logic [J].
Jude Iloabuchi Obianyo ;
Okey Enangha Okey ;
George Uwadiegwu Alaneme .
Innovative Infrastructure Solutions, 2022, 7