The Major Causes of Construction Delays Identified Using the Delphi Technique: Perspectives of Contractors and Consultants in Thailand

被引:0
作者
Nutchapongpol Kongchasing
Gritsada Sua-Iam
机构
[1] Rajamangala University of Technology Phra Nakhon (RMUTP),Department of Civil Engineering, Faculty of Engineering
来源
International Journal of Civil Engineering | 2021年 / 19卷
关键词
Delphi technique; Contractors; Consultants; Construction delay; Construction;
D O I
暂无
中图分类号
学科分类号
摘要
At present, in the Bangkok Metropolitan Area of Thailand, numerous construction projects are in process or have recently been brought to completion. In pursuing this work, contractors regularly face construction delay problems, many of which are likely to have been avoidable. The research objective is to survey and prioritize the factors leading to construction delays from the perspective of both the consultants and the contractors. Data were collected via a survey instrument and the Delphi technique was used as the research methodology. To identify the factors that lead to construction delays relevant to the study context, a panel of experts comprising 18 construction public company leaders and 17 project engineers and 17 project consultants, 1 from each of the largest construction contractor and consultant companies in Thailand, and 20 academics in the field of construction were invited to share their opinions. Eventually, 13 factors leading to construction delays were identified from the data collected from the expert panel. A questionnaire was generated using a Likert scale with a range of 1–5 based on the factors suggested by the experts’ opinions. A total of 17 respondents from the contractor companies and 17 respondents from the consultant companies responded to the questionnaire. The numeric value of the responses was computed using the Delphi technique. The responses reached constancy at the second round of data collection. According to the statistical analysis, a Shortage of qualified labor was the most important factor leading to construction delays, according to both the contractors’ and the consultants’ perspectives with a mean value of 4.65 and 4.53, respectively. Change orders made by owners were the second most important factor according to both the contractors and the consultants with a mean value of 4.24 and 4.28, respectively. In addition, insufficient financial liquidity on the part of the contractor ranked as the third most important reason according to both the contractors and the consultants with a mean value of 4.18 and 4.12, respectively. The outcomes are applicable to the causes of construction delay in the Bangkok Metropolitan Area of Thailand, but may not be applicable to other settings. A review of the literature suggests significant differences in relation to such matters as the regulatory environment, societal practices and expectations, economic considerations, the environment, technology, and religion across settings may have an impact on what causes construction delays.
引用
收藏
页码:319 / 338
页数:19
相关论文
共 97 条
  • [1] Djajić S(2015)Guest workers in the underground economy Labour Econ 35 53-62
  • [2] Mesnard A(2019)Analysing causal relationships between delay factors in construction projects a case study of Iran Int J Manag Proj Bus 64 73-81
  • [3] Rezaee JM(2018)Does company size matter? Validation of an integrative model of safety behavior across small and large construction companies J Saf Res 28 158-164
  • [4] Yousefi S(2018)Building resilience: knowledge, experience and perceptions among informal construction stakeholders Int J Disaster Risk Reduct 17 1715-1727
  • [5] Chakrabortty KR(2019)Analysis of stakeholder concerns at different times of construction projects using Social network Analysis (SNA) Int J Civ Eng 14 161-170
  • [6] Guo WHB(2016)Quantitative risk allocation in construction projects using cooperative-bargaining game theory Int J Civ Eng 145 932-939
  • [7] Yiu WT(2016)Using PIPS to minimize causes of delay in Saudi Arabian construction projects: university case study Procedia Eng 17 550-560
  • [8] González AV(2018)Factor selection for delay analysis using knowledge discovery in databases Autom Constr 26 665-674
  • [9] Chmutina K(2016)Delays in construction projects: the case of Jordan Int J Proj Manag 7 120-125
  • [10] Rose J(2019)Causes of delay in construction projects: a quantitative analysis Eng Constr Archit Manag 21 525-544