Integrated non-cyclical preventive maintenance scheduling and production planning for multi-parallel component production systems with interdependencies-induced degradation

被引:0
作者
Ziyad Bahou
Mohamed Reda Lemnaouar
Issam Krimi
机构
[1] Mohammed V University in Rabat,Mohammadia School of Engineers
[2] Mohammed V University in Rabat,Superior School of Technology Salé, LASTIMI
[3] Abu Dhabi University,College of Engineering
来源
The International Journal of Advanced Manufacturing Technology | 2024年 / 130卷
关键词
Production planning; Interdependencies-induced degradation; Preventive maintenance scheduling; Ordinary differential system; Integer programming;
D O I
暂无
中图分类号
学科分类号
摘要
Integrating preventive maintenance (PM) scheduling and production planning efficiently remains challenging for researchers and practitioners alike, owing to complex component interdependencies. Existing studies often lack practicality due to oversimplified assumptions. In this paper, we propose a two-stage solution for the integrated PM scheduling and production planning problem within multi-parallel component manufacturing systems, accounting for diverse interdependencies. These interdependencies encompass stochastic, structural, economic, and resource-related interdependencies, all while accounting for the resultant degradation. The primary objective is jointly optimizing costs associated with holding, backorders, production, setup, and maintenance. Initially, we employ an Ordinary Differential System to compute a realistic production capacity. Additionally, we analyze the effects of interdependence-induced degradation on system availability and failures. Subsequently, we formulate the problem as an integer programming model to determine an optimal joint plan. The effectiveness of our approach is validated through numerical examples and sensitivity analysis, providing insightful guidance for efficient PM scheduling and production planning, particularly in large-scale production systems.
引用
收藏
页码:4723 / 4749
页数:26
相关论文
共 191 条
[51]  
Gackowiec P(2013)An optimal production planning and maintenance policy for a multiple-product and single machine under failure rate dependency IFAC Proceedings Volumes 46 2159-317
[52]  
DerakhshanHoreh S(2012)Integrating noncyclical preventive maintenance scheduling and production planning for a single machine Int J Prod Econ 136 1468-66
[53]  
Bijari M(2009)An integrated production planning model with load-dependent lead-times and safety stocks Comput & Chem Eng 33 145-506
[54]  
Xia T(2020)Condition-based maintenance planning for systems subject to dependent soft and hard failures IEEE Trans Reliab 70 297-186
[55]  
Jin X(2015)Maintenance planning and dynamic grouping for multi-component systems with positive and negative economic dependencies IMA J Manag Math 26 425-628
[56]  
Xi L(2007)Production planning with load dependent lead times: an update of research Ann Oper Res 153 201-undefined
[57]  
Ni J(2011)On modeling with multiplicative differential equations Appl Math-A J Chinese Universities 26 11614-undefined
[58]  
Biel K(2023)Mathematical modeling and analysis of the dynamics of RNA viruses in presence of immunity and treatment: A case study of SARS-CoV-2 Vaccines 11 305-undefined
[59]  
Glock CH(2022)A generalized distributed delay model for hepatitis B virus infection with two modes of transmission and adaptive immunity: A mathematical study Math Methods Appl Sci 45 294-undefined
[60]  
Allahverdi A(2013)Parameter uncertainty in biochemical models described by ordinary differential equations Math Biosci 246 59-undefined