New heuristics for the no-wait flowshop with sequence-dependent setup times problem

被引:0
作者
Marcelo Seido Nagano
Daniella Castro Araújo
机构
[1] University of São Paulo,School of Engineering of São Carlos
[2] Production Engineering,undefined
来源
Journal of the Brazilian Society of Mechanical Sciences and Engineering | 2014年 / 36卷
关键词
Heuristic; No-wait flowshop; Sequence-dependent setup; Makespan; Total flowtime;
D O I
暂无
中图分类号
学科分类号
摘要
In this paper, we address the problem of scheduling jobs in a no-wait flowshop with sequence-dependent setup times with the objective of minimizing the makespan and the total flowtime. As this problem is well known for being NP hard, we present two new constructive heuristics to obtain good approximate solutions for the problem in a short CPU time, named GAPH and QUARTS. GAPH is based on a structural property for minimizing makespan and QUARTS breaks the problem in quartets to minimize the total flowtime. Experimental results demonstrate the superiority of the proposed approaches over three of the best-known methods in the literature: BAH and BIH, from Bianco et al. (INFOR J 37(1):3–19, 1999) and TRIPS, by Brown et al. (J Oper Res Soc 55(6):614–621, 2004).
引用
收藏
页码:139 / 151
页数:12
相关论文
共 69 条
[1]  
Aldowaisan T(2003)New heuristics for no-wait flowshops to minimize makespan Comput Oper Res 30 1219-1231
[2]  
Allahverdi A(2000)No-wait and separate setup three-machine flowshop with total completion time criterion Int Trans Oper Res 7 245-264
[3]  
Allahverdi A(1999)A review of scheduling research involving setup considerations Omega Int J Manag Sci 27 219-239
[4]  
Aldowaisan T(2001)Minimizing total completion time in a no-wait flowshop with sequence-dependent additive changeover times J Oper Res Soc 52 449-462
[5]  
Allahverdi A(2008)A survey of scheduling problems with setups times or costs Eur J Oper Res 187 985-1032
[6]  
Gupta JND(2008)The significance of reducing setup times/setup costs Eur J Oper Res 187 978-984
[7]  
Aldowaisan T(1999)Flow shop no-wait scheduling with sequence-dependent setup times and release dates INFOR J 37 3-19
[8]  
Allahverdi A(2004)Total flowtime and makespan for a no-wait m-machine flowshop with set-up times separated J Oper Res Soc 55 614-621
[9]  
Aldowaisan T(2010)A bicriteria m-machine flowshop scheduling with sequence dependent setup times Appl Math Model 34 284-293
[10]  
Allahverdi A(2003)Solving the continuos flow-shop scheduling problem by metaheuristics Eur J Oper Res 151 400-414