Numerical Simulations of Construction of Shield Tunnel with Small Clearance to Adjacent Tunnel without and with Isolation Pile Reinforcement

被引:49
|
作者
Lv, Jianbing [1 ]
Li, Xulong [1 ]
Li, Zhanrong [2 ]
Fu, Helin [3 ]
机构
[1] Guangdong Univ Technol, Coll Civil & Transportat Engn, Guangzhou 510000, Guangdong, Peoples R China
[2] China Tunnel Construct Co Ltd, Guangzhou 510000, Guangdong, Peoples R China
[3] Cent S Univ, Sch Civil Engn, Changsha 410012, Hunan, Peoples R China
基金
中国国家自然科学基金;
关键词
Small spacing; Shield construction; Bored pile reinforcement; Numerical simulation; Settlement; Deformation monitoring; DISTANCE;
D O I
10.1007/s12205-020-1167-y
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In the process of building subways in many cities, the technology of shield tunneling has become more widely used. In large cities, it is inevitable for the tunnels to pass through the foundations of buildings or between deep piles of bridges. Due to the many restrictions on urban space in China, the clearance between two tunnels has also become smaller. Hence, it is an urgent technical problem to resolve the mutual influence of the close construction of two tunnels using shield technology. In this study, the shield construction project of two tunnels with a small clearance of 2.6 m has been analyzed. The project is between Tongdewei Station and Shangbu Station in the northern extension section of the Guangzhou Metro Line 8. The main parameters used in the analyses are the tunnel lining deformation and the ground settlement. The construction without and with the isolation pile reinforcement have been simulated numerically. The simulation results have been compared with the on-site monitoring data. Based on the comparison, it shows that with the reinforcement, the tunnel lining deformation and the ground settlement can be reduced significantly. The effect of subway shield construction on the construction of the first subway tunnel will significantly reduce. The deformation of the shield excavation net width and the mutual influence can also be greatly reduced. The findings from this study can be used as technical foundation and reference for the construction of similar projects, i.e. shield tunnel construction with a small clearance between tunnels.
引用
收藏
页码:295 / 309
页数:15
相关论文
共 24 条
  • [1] Numerical Simulations of Construction of Shield Tunnel with Small Clearance to Adjacent Tunnel without and with Isolation Pile Reinforcement
    Jianbing Lv
    Xulong Li
    Zhanrong Li
    Helin Fu
    KSCE Journal of Civil Engineering, 2020, 24 : 295 - 309
  • [2] Deformation and Reinforcement of the Existing Tunnel Affected by New Shield Tunnel Construction with Small Clearance
    Zhang, Junchao
    Yu, Jiacheng
    Li, Cunjun
    Liu, Yizhou
    Tian, Longgang
    He, Yonglin
    Zhang, Qi
    BUILDINGS, 2025, 15 (02)
  • [3] Numerical analysis of Hefei metro shield tunnel construction crossing pile foundation of building
    Ding, Kewei
    Man, Dawei
    CIVIL ENGINEERING AND URBAN PLANNING III, 2014, : 245 - 248
  • [4] Safety Assessment of Tunnel Shield Construction for Existing Adjacent Bridges
    Zhu, Lei
    Liang, Chengcheng
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2022, 2022
  • [5] Grouting Reinforcement Measures for a Shield Tunnel Undercrossing Foundation of a Pile Group
    Tang, Jinsong
    Bi, Yingqian
    Zhang, Bao
    INTERNATIONAL JOURNAL OF GEOMECHANICS, 2024, 24 (10)
  • [6] Risk assessment of shield construction adjacent to the existing shield tunnel based on improved nonlinear FAHP
    Guo, Desai
    Meng, Fanyan
    Wu, Huaina
    Yang, Xinxin
    Chen, Renpeng
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2025, 155
  • [7] Numerical analysis of the influence of underpinning pile affected by overlapping tunnel with shield method
    Ou, Ping
    Yuan, Hong
    Hu, Shifeng
    Yang, Xiongfei
    PROCEEDINGS OF THE 2017 2ND INTERNATIONAL CONFERENCE ON ADVANCES IN MATERIALS, MECHATRONICS AND CIVIL ENGINEERING (ICAMMCE 2017), 2017, 121 : 108 - 113
  • [8] Impact of Double-O-Tube Shield Tunnel Construction on Adjacent Buildings
    Wei Xinjiang
    Hong Jie
    Wei Gang
    DISASTER ADVANCES, 2012, 5 (04): : 1744 - 1748
  • [9] Analysis and Discussion on Surface Settlement induced by Shield Tunnel Construction of Adjacent Sructure
    Ding Zhi
    Wei Xin-Jiang
    Zhang Tao
    Ge Guo-Bao
    DISASTER ADVANCES, 2012, 5 (04): : 341 - 345
  • [10] Analysis of effects on city metro tunnel due to adjacent pile foundation construction
    Hangzhou Xiaoshan Urban Construction Investment Group Co., Ltd, Hangzhou
    Zhejiang
    311202, China
    不详
    Zhejiang
    310012, China
    Rock Soil Mech, (577-582): : 577 - 582