Reactive Procedure for Robust Project Scheduling under the Activity Disruptions

被引:5
|
作者
Li, Lei [1 ]
Liu, Wanlin [1 ]
Chen, Yumeng [1 ]
Yang, Shun [1 ]
机构
[1] Sichuan Agr Univ, Coll Architecture & Urban Rural Planning, Chengdu 611830, Peoples R China
关键词
Y Project scheduling; Reactive procedure; Robustness; Activity disruptions; Genetic algorithm; MATHEMATICAL-MODEL; GENETIC ALGORITHM; CLASSIFICATION; HEURISTICS;
D O I
10.1007/s12205-021-1555-y
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The baseline schedule may become infeasible when disruptions happen during the execution of project. This will lead to project delays and financial losses. In this paper, we developed a robust reactive optimization model. Our objective is to maximize the robustness of reactive schedule. Moreover, a robust reactive procedure is proposed for baseline schedule under a series of disruptions caused by activity duration. To test the proposed approach, sets of J60 and J90 instances from the Project Scheduling Library (PSPLIB) were used. Meanwhile, we tested the reactive project scheduling with the aim of minimizing makespan and compared the maximal robustness reactive schedule and the minimal makespan reactive schedule. We developed a reactive procedure involving genetic algorithm for reactive scheduling due to its non-deterministic polynomial hard (NP-hard). The results indicated that robust reactive scheduling has the advantage in maintaining the schedule's ability of tolerating variabilities and reducing the impact of activity disruptions on the makespan. The research results can help project managers develop a robust schedule which can tolerate variabilities in a random environment.
引用
收藏
页码:3213 / 3222
页数:10
相关论文
共 50 条
  • [1] Reactive Procedure for Robust Project Scheduling under the Activity Disruptions
    Lei Li
    Wanlin Liu
    Yumeng Chen
    Shun Yang
    KSCE Journal of Civil Engineering, 2021, 25 : 3213 - 3222
  • [2] Pro-Reactive Approach for Project Scheduling Under Unpredictable Disruptions
    Zaman, Forhad
    Elsayed, Saber
    Sarker, Ruhul
    Essam, Daryl
    Coello, Carlos A. Coello
    IEEE TRANSACTIONS ON CYBERNETICS, 2022, 52 (11) : 11299 - 11312
  • [3] On the Robust and Stable Flowshop Scheduling Under Stochastic and Dynamic Disruptions
    Liu, Feng
    Wang, Shengbin
    Hong, Yuan
    Yue, Xiaohang
    IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, 2017, 64 (04) : 539 - 553
  • [4] Robust and reactive project scheduling: a review and classification of procedures
    Herroelen, W
    Leus, R
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2004, 42 (08) : 1599 - 1620
  • [5] Robust project scheduling integrated with materials ordering under activity duration uncertainty
    Zhang, Yan
    Cui, Nanfang
    Hu, Xuejun
    Hu, Zhentao
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2020, 71 (10) : 1581 - 1592
  • [6] Reactive project scheduling method to enhance project progress under uncertainty
    Suwa, Haruhiko
    Morita, Daisuke
    JOURNAL OF ADVANCED MECHANICAL DESIGN SYSTEMS AND MANUFACTURING, 2016, 10 (03):
  • [7] Multi-mode resource constrained project scheduling under resource disruptions
    Chakrabortty, Ripon K.
    Sarker, Ruhul A.
    Essam, Daryl L.
    COMPUTERS & CHEMICAL ENGINEERING, 2016, 88 : 13 - 29
  • [8] A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration
    Moradi, Hadi
    Shadrokh, Shahram
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2019, 57 (10) : 3138 - 3167
  • [9] A Literature Review on Robust Project Scheduling Under Uncertainty
    Li, Jun-ting
    Zheng, Ming-zhu
    2018 INTERNATIONAL CONFERENCE ON COMMUNICATION, NETWORK AND ARTIFICIAL INTELLIGENCE (CNAI 2018), 2018, : 131 - 136
  • [10] Reactive Strategies in the Multiproject Scheduling with Multifactor Disruptions
    Wang, Weixin
    Su, Jiafu
    Xu, Jin
    Ge, Xianlong
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2020, 2020