A methodology for evaluation and classification of rock mass quality on tunnel engineering

被引:44
作者
Chen, Chao-Shi [1 ]
Liu, Ya-Ching [1 ]
机构
[1] Natl Cheng Kung Univ, Dept Resources Engn, Tainan 70101, Taiwan
关键词
rock mass classification; fuzzy Delphi method; analytic hierarchy process;
D O I
10.1016/j.tust.2006.10.003
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In this paper a new methodology for evaluation and classification of rock mass quality that can be applied to rock tunneling is presented. An evaluation model based on combing the analytic hierarchy process (AHP) and the fuzzy Delphi method (FDM) for assessing the rock mass rating is the main procedure. This research treats rock mass classification as a group decision problem, and applies the fuzzy logic theory as the criterion to calculate the weighting of factors. The main advantage of this procedure is that it can effectively change the weighting of each rating parameter with the variation of geological conditions. The proposed method was evaluated and applied to the actual cases that are the two tunnels along the Second Northern Highway around Taipei area in Taiwan, namely Mu-Zha and Hsin-Tien tunnels. It was found that the determined results were in a good agreement with the original data assessed by the RMR. Results of the analyses show. that it can be provided a more quantitative measure of rock mass and hence minimize judgmental bias. The proposed method should be more feasible for future tunnel construction and for suggestions of tunnel support design in the geological area of Taiwan. (c) 2006 Elsevier Ltd. All rights reserved.
引用
收藏
页码:377 / 387
页数:11
相关论文
共 11 条
  • [1] [Anonymous], 1975, 2 AUSTR NZ C GEOM I
  • [2] Barton NR., 1974, Rock Mechanics, V6, P189
  • [3] BIENIAWSKI ZT, 1979, 4TH P INT C ROCK MEC, V2, P41
  • [4] Bieniawski ZT., 1973, The Civil Engineer in South Africa, V15, P335
  • [5] Bieniawski ZT., 1989, Engineering rock mass classification, P251
  • [6] Kaufmann A, 1988, FUZZY MATH MODELS EN
  • [7] *MIN TRANSP COMM T, 1999, INTRO TUNN ENG 2 NO
  • [8] RABCEWICZ LV, 1964, NEW AUSTR TUNNELING, V16
  • [9] RABCEWICZ LV, 1964, NEW AUSTR TUNNELING, V17
  • [10] Saaty TL., 1980, The Analytic Hierarchy Process: Planning, Priority Setting, Resource Allocation