Truck fleet size selection in open-pit mines based on the match factor using a MINLP model

被引:11
作者
Mohtasham, Mehrnaz [1 ]
Mirzaei-Nasirabad, Hossein [1 ]
Askari-Nasab, Hooman [2 ]
Alizadeh, Behrooz [3 ]
机构
[1] Sahand Univ Technol, Fac Min Engn, Tabriz, Iran
[2] Univ Alberta, Fac Min & Petr Engn, Edmonton, AB, Canada
[3] Sahand Univ Technol, Fac Basic Sci, Tabriz, Iran
关键词
Truck fleet sizing; MINLP model; match factor; simulation; open-pit mines; EQUIPMENT SELECTION; EXPERT-SYSTEM; OPTIMIZATION; SIMULATION; MANAGEMENT; ALGORITHM;
D O I
10.1080/25726668.2021.1919374
中图分类号
TD [矿业工程];
学科分类号
0819 ;
摘要
The present study aims to propose new strategies based on mixed-integer non-linear programming (MINLP) models for the equipment sizing (ES) problem to verify the overall efficiency of the fleet. The developed models estimate the optimal size of trucks concerning the match factor value with two different strategies. The first strategy deals with each loader type, and the second one is applied simultaneously with all types of loaders. The proposed approaches are compared to a simulation strategy to assess the models. Implementing models with a copper mine case study provides a more efficient haul fleet size than the decisions offered by the simulation method. Moreover, the presented strategies provide an effective way to improve equipment performance where the current mine strategy does not adapt well. A key contribution of this research is the development, implementation, and verification of new optimization and simulation methods to address the ES problem in open-pit mines.
引用
收藏
页码:159 / 175
页数:17
相关论文
共 44 条
  • [1] Al-Hassan S., 2007, GHANA MINING J, V9, DOI [10.4314/gm.v9i1.42606, DOI 10.4314/GM.V9I1.42606]
  • [2] Alarie S., 2002, INT J SURFACE MINING, V16, P59, DOI [10.1076/ijsm.16.1.59.3408, DOI 10.1076/IJSM.16.1.59.3408]
  • [3] EXPERT SYSTEM FOR EQUIPMENT SELECTION FOR EARTH-MOVING OPERATIONS
    AMIRKHANIAN, SN
    BAKER, NJ
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1992, 118 (02): : 318 - 331
  • [4] Ataeepour N., 1999, International Journal of Surface Mining, Reclamation and Environment, V13, P125, DOI DOI 10.1080/09208119908944228
  • [5] Predicting equipment requirements using SIMAN simulation - a case study
    Awuah-Offei, K
    Temeng, VA
    Al-Hassan, S
    [J]. TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY SECTION A-MINING TECHNOLOGY, 2003, 112 : 180 - 184
  • [6] Bandopadhyay, 2002, INT J SURF MIN RECLA, V16, P163, DOI [10.1076/ijsm.16.3.163.7420, DOI 10.1076/IJSM.16.3.163.7420]
  • [7] An application of the analytic hierarchy process in equipment selection at Orhaneli open pit coal mine
    Bascetin, A
    [J]. TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY SECTION A-MINING TECHNOLOGY, 2004, 113 (03): : 192 - 199
  • [8] Deriving preference order of open pit mines equipment through MADM methods: Application of modified VIKOR method
    Bazzazi, Abbas Aghajani
    Osanloo, Morteza
    Karimi, Behrooz
    [J]. EXPERT SYSTEMS WITH APPLICATIONS, 2011, 38 (03) : 2550 - 2556
  • [9] Sizing equipment for open pit mining - a review of critical parameters
    Bozorgebrahimi, E
    Hall, RA
    Blackwell, GH
    [J]. TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY SECTION A-MINING TECHNOLOGY, 2003, 112 : 171 - 179
  • [10] Burt C., 2008, OPTIMISATION APPROAC