Comparison of shallow tunneling method with pile and rib method for construction of subway station in soft ground

被引:7
作者
Amiri, Sina [1 ]
Dehghan, Ali Naghi [1 ]
机构
[1] Islamic Azad Univ, Dept Min Engn, Sci & Res Branch, Tehran, Iran
关键词
shallow tunneling method; pile and rib method; ground surface settlement; subway station construction; numerical modeling; STABILITY ANALYSIS; SETTLEMENT; OPTIMIZATION; PROPAGATION; PREDICTION;
D O I
10.1007/s11709-021-0746-4
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In the present study, a comparison between the new shallow tunneling method (STM) and the traditional pile and rib method (PRM) was conducted to excavate and construct subway stations in the geological conditions of Tehran. First, by selecting Station Z6 located in the Tehran Subway Line 6 as a case study, the construction process was analyzed by PRM. The maximum ground settlement of 29.84 mm obtained from this method was related to the station axis, and it was within the allowable settlement limit of 30 mm. The acceptable agreement between the results of numerical modeling and instrumentation data indicated the confirmation and accuracy of the excavation and construction process of Station Z6 by PRM. In the next stage, based on the numerical model validated by instrumentation data, the value of the ground surface settlement was investigated during the station excavation and construction by STM. The results obtained from STM showed a significant reduction in the ground surface settlement compared to PRM. The maximum settlement obtained from STM was 6.09 mm as related to the front of the excavation face. Also, the sensitivity analysis results denoted that in addition to controlling the surface settlement by STM, it is possible to optimize some critical geometric parameters of the support system during the station excavation and construction.
引用
收藏
页码:704 / 717
页数:14
相关论文
共 32 条
[1]  
Alebouyeh A, 2019, TUNNELS UNDERGROUND, P5264
[2]  
Avanaki MJ., 2019, SEISMIC PERFORMANCE, P5685
[3]   Evaluating the effect of EPBM operational parameters on surface settlement in soft ground [J].
Dehghan, Ali Naghi ;
Bagheri, Ehsan ;
Khodaei, Meysam ;
Kalehsar, Rouzbeh Imani .
JOURNAL OF GEOPHYSICS AND ENGINEERING, 2021, 18 (01) :47-61
[4]   Influence of Forepoling Umbrella on the Settlements Induced by Shallow Urban Tunneling [J].
Dehghan, Ali Naghi .
GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2020, 38 (05) :5005-5022
[5]   3D Numerical Modeling of the Propagation of Hydraulic Fracture at Its Intersection with Natural (Pre-existing) Fracture [J].
Dehghan, Ali Naghi ;
Goshtasbi, Kamran ;
Ahangari, Kaveh ;
Jin, Yan ;
Bahmani, Aram .
ROCK MECHANICS AND ROCK ENGINEERING, 2017, 50 (02) :367-386
[6]   3-D stability analysis and design of the primary support of Karaj metro Tunnel: Based on convergence data and back analysis algorithm [J].
Dehghan, Ali Naghi ;
Shafiee, Seyed Mohsen ;
Rezaei, Fereydoun .
ENGINEERING GEOLOGY, 2012, 141 :141-149
[7]  
Executive Yuan 1021 Railway Accident Administrative Investigation Team, 2018, REP DES CONSTR METH
[8]   Shallow tunnelling method (STM) for subway station construction in soft ground [J].
Fang, Qian ;
Zhang, Dingli ;
Wong, Louis Ngai Yuen .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2012, 29 :10-30
[9]   Determining the domain of in situ stress around Marun Oil Field's failed wells, SW Iran [J].
Farsimadan, Meisam ;
Dehghan, Ali Naghi ;
Khodaei, Meysam .
JOURNAL OF PETROLEUM EXPLORATION AND PRODUCTION TECHNOLOGY, 2020, 10 (04) :1317-1326
[10]   Optimization of site exploration program for improved prediction of tunneling-induced ground settlement in clays [J].
Gong, Wenping ;
Luo, Zhe ;
Juang, C. Hsein ;
Huang, Hongwei ;
Zhang, Jie ;
Wang, Lei .
COMPUTERS AND GEOTECHNICS, 2014, 56 :69-79