Removal and deconstruction of Maureen Alpha Platform. The world largest gravity based steel platform

被引:0
|
作者
Kristing, K [1 ]
机构
[1] Aker Kvaerner Offshore Partner AS, Stavanger, Norway
关键词
D O I
暂无
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
After 16 years of field production, the Phillips Maureen Alpha Platform (110.000 tons) was refloated and towed from the field in June 2001 to a deep water mooring site on the West coast of Norway, for deconstruction. To date, this platform is the largest and heaviest offshore production platform to be removed from an offshore location as part of decommissioning operations. At its inshore location, the modules were lifted from the floating platform prior to being submerged to facilitate de-mating the deck onto a barge and subsequent onshore skidding operation. The substructure and storage tanks were cut in smaller pieces whilst maintaining an even distribution of weight whilst floating. These smaller pieces were transferred to onshore for further deconstruction. All of the complicated engineering and delicate marine operations went completely according to plan. The final reuse/recycle figure for the platform and the loading buoy amounts to 99.5%.
引用
收藏
页码:478 / 485
页数:8
相关论文
共 50 条
  • [1] FOUNDATION DESIGN OF THE MAUREEN STEEL GRAVITY PLATFORM.
    Broughton, Peter
    Wright, Stephen J.
    Magris, E.
    European Petroleum Conference, 1980, 2 : 235 - 243
  • [2] Removal of the Maureen steel gravity platform
    不详
    JOURNAL OF PETROLEUM TECHNOLOGY, 2000, 52 (04): : 56 - +
  • [3] Removal of the Maureen steel gravity platform
    Broughton, P.
    Davies, R.L.
    Jenkins, J.
    Proceedings of the Annual Offshore Technology Conference, 1999, 3 : 593 - 606
  • [4] Deconstruction of the Maureen platform and loading column
    Broughton, P
    Davies, RL
    Green, M
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-MARITIME ENGINEERING, 2004, 157 (01) : 3 - 21
  • [5] Foundation design for the refloat of the Maureen steel gravity platform
    Broughton, P
    Davies, RL
    Aldridge, T
    Carrington, T
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-GEOTECHNICAL ENGINEERING, 2002, 155 (02) : 111 - 118
  • [6] Discussion: Deconstruction of the Maureen platform and loading column
    Broughton, R
    Davies, RL
    Green, M
    Fish, PB
    Rogers, S
    Smedley, P
    Banning-Lover, M
    French, S
    Smith, D
    Knight, M
    Faye, C
    Sandberg, N
    Read, P
    Hughes, N
    Glover, N
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-MARITIME ENGINEERING, 2005, 158 (02) : 85 - 88
  • [7] INNOVATIVE CONCRETE GRAVITY PLATFORM.
    Anon
    Ocean Industry, 1976, 11 (03):
  • [8] INSTALLATION OF MAUREEN GRAVITY PLATFORM OVER A TEMPLATE
    MYRABO, DO
    DORIS, CG
    BERTHIN, JC
    WORLD OIL, 1985, 200 (05) : 117 - 117
  • [9] STEEL GRAVITY PLATFORM POSITIONING OVER TEMPLATE ON THE NORTH-SEA MAUREEN FIELD
    SOHOLT, JE
    PARUZZOLO, A
    MAZZON, A
    BECCEGATO, L
    JOURNAL OF PETROLEUM TECHNOLOGY, 1983, 35 (01): : 247 - 254
  • [10] EFFECTS OF SOIL-STRUCTURE INTERACTION ON SEISMIC RESPONSE OF A STEEL GRAVITY PLATFORM.
    Veletsos, A.S.
    Boaz, I.B.
    Proceedings of the Annual Offshore Technology Conference, 1979, v (01): : 413 - 425