Sensitivity Analysis of the Constructive Parameters for the 2 x 25-kV High-Speed Railway Lines Planning

被引:22
作者
Brenna, Morris [1 ]
Foiadelli, Federica [1 ]
机构
[1] Politecn Milan, Dept Energy, I-20156 Milan, Italy
关键词
Autotransformer; current distribution; high-speed trains; line inductance; railway lines planning;
D O I
10.1109/TPWRD.2010.2042977
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
This paper presents a study of the AC 2 x 25 kV-50-Hz system for the train power supply, giving a valid instrument for better design of the future railway lines. In fact, different constructive solutions, such as the autotransformer short-circuit voltage, can influence the correct working of the system. The analysis of the real currents distribution between the 2 x 25-kV system branches is presented, overcoming the circuital simplifications adopted in the traditional studies that have now been documented in the literature. The study is validated through simulation and in-field measurements.
引用
收藏
页码:1923 / 1931
页数:9
相关论文
共 14 条
[11]  
Pilo E, 2000, 2000 IEEE POWER ENGINEERING SOCIETY SUMMER MEETING, CONFERENCE PROCEEDINGS, VOLS 1-4, P1053, DOI 10.1109/PESS.2000.867519
[12]  
PILO E, 2003, IEEE ASME JOINT RAIL
[13]  
Popescu Mihaela, 2008, WSEAS Transactions on Systems, V7, P689
[14]  
SENOL I, 1998, P 9 MED EL C MAY 18, V2, P885