Switchgear component commonality design based on trade-off analysis among inventory level, delivery lead-time and product performance

被引:5
作者
Izui, Kazuhiro [1 ]
Nishiwaki, Shinji [1 ]
Yoshimura, Masataka [1 ]
Kariya, Haruki [1 ]
Ogihara, Yoshiya [2 ]
Hayashi, Shuichi [2 ]
机构
[1] Kyoto Univ, Dept Aeronaut & Astronaut, Kyoto 6068501, Japan
[2] Nisshin Elect Co Ltd, Kyoto 6158686, Japan
关键词
component commonalisation; inventory cost; delivery lead-time; multiobjective optimisation; trade-off analysis; GENETIC ALGORITHM; FAMILY DESIGN; VARIETY OPTIMIZATION; GROUP-TECHNOLOGY; SYSTEMS; DEMAND; ARCHITECTURE;
D O I
10.1080/00207540902791868
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The shortening of product delivery lead-times can usually be achieved by keeping high-level components in inventory, however in small-volume production systems, maintaining such inventories is often a costly as well as a risky business strategy. If the risk of maintaining unsold inventory can be decreased, even small-volume manufacturers may be able to justify holding more significant quantities of versatile inventory. This paper discusses a component commonality effect to breakthrough the trade-off relationship between inventory levels and delivery lead-times for such small-volume production systems. By using the same component in different products, inventory maintenance costs can be dramatically reduced, but component commonality design problems are inherently complex, since excessive module commonality may lead to lower product performances, and there are trade-off relationships between product performance and cost reductions obtained through component commonality. In this paper, such a design problem is formulated as a multiobjective component commonality design optimisation problem considering inventory level, delivery lead-time and product performance, and the optimal solutions are obtained as a Pareto optimal solution set. Detailed procedures concerning the proposed design method, including inventory simulation, are discussed and developed for a switchgear design problem. Finally, an example switchgear design problem is solved to illustrate that optimal use of component commonalities across different modules can significantly reduce inventory costs, while also shortening product delivery lead-times.
引用
收藏
页码:2821 / 2840
页数:20
相关论文
共 28 条
  • [1] BURBIDGE JL, 1982, INT J PROD RES, V20, P339
  • [2] MODROC - AN EXTENSION OF RANK ORDER CLUSTERING FOR GROUP TECHNOLOGY
    CHANDRASEKHARAN, MP
    RAJAGOPALAN, R
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1986, 24 (05) : 1221 - 1233
  • [3] A genetic algorithm based method for product family design optimization
    D'Souza, B
    Simpson, TW
    [J]. ENGINEERING OPTIMIZATION, 2003, 35 (01) : 1 - 18
  • [4] A fast and elitist multiobjective genetic algorithm: NSGA-II
    Deb, K
    Pratap, A
    Agarwal, S
    Meyarivan, T
    [J]. IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, 2002, 6 (02) : 182 - 197
  • [5] Du XH, 2002, CONCURRENT ENG-RES A, V10, P113, DOI [10.1177/1063293X02010002635, 10.1106/106329302027635]
  • [6] DETERMINING SAFETY STOCK IN THE PRESENCE OF STOCHASTIC LEAD TIME AND DEMAND
    EPPEN, GD
    MARTIN, RK
    [J]. MANAGEMENT SCIENCE, 1988, 34 (11) : 1380 - 1390
  • [7] Development of an algorithm for the application of Group Technology in the design of Manufacturing Systems
    Escoto, RP
    McDonnell, LR
    Salort, EV
    Esteban, FCL
    [J]. PRODUCTION PLANNING & CONTROL, 1998, 9 (03) : 267 - 274
  • [8] Product variety optimization simultaneously designing module combination and module attributes
    Fujita, K
    Yoshida, H
    [J]. CONCURRENT ENGINEERING-RESEARCH AND APPLICATIONS, 2004, 12 (02): : 105 - 118
  • [9] Product variety optimization under modular architecture
    Fujita, K
    [J]. COMPUTER-AIDED DESIGN, 2002, 34 (12) : 953 - 965
  • [10] GALLAGHER CC, 1971, INT J PROD RES, V9, P229