Risk assessment of sewage treatment Public Private Partnership projects in China

被引:3
作者
Zhao, Hui [1 ]
Zhang, Jingqi [1 ]
Li, Zhijie [1 ]
机构
[1] Qingdao Univ Technol, Sch Management Engn, Qingdao 266520, Peoples R China
关键词
Public Private Partnership; Sewage treatment; Critic method; TOSIS method; Risk assessment; China;
D O I
10.5004/dwt.2022.28108
中图分类号
TQ [化学工业];
学科分类号
0817 ;
摘要
With the deepening of ecological civilization construction, the water pollution caused by the discharge of industrial wastewater and domestic sewage has attracted people's extensive attention. Sewage treatment project is becoming more and more important as an important work of water pollution control. In order to reduce the financial pressure of the government and improve the efficiency of the industry, more and more sewage treatment projects adopt the Public Private Partnership (PPP) financing mode. However, the PPP financing mode of the project has the characteristics of long construction cycle, long investment recovery period, many participants and so on, the project implementation process is faced with more and complex risks, how to effectively carry out the risk management of sewage treatment PPP project is the key to the success of the project. In this paper, the Principal Component Analysis (PCA) is firstly used to reduce the dimension of the risk factor set, and then the risk assessment index system is obtained after further generalization and sorting. On this basis, considering the correlation between the indicators. Use Criteria Importance Though Intercrieria Correlation (CRITIC) objective weighting method to give weight to the indicators. Secondly, the risk assessment model of sewage treatment PPP project is established by using Technique for Order Preference by Similarity to an Ideal Solution (TOPSIS) multi-objective decision-making method. Finally apply the model to the Shanghai city Bailonggang sewage treatment project risk evaluation, the results show that the operation process of sewage disposal PPP projects need to focus on professional talents loss of monitoring and control, construction safety, the effects of government credit risks, and the sensitivity analysis to verify the feasibility and effectiveness of the proposed selection model. It is hoped that the above research can provide useful reference for the construction risk assessment of sewage treatment PPP projects.
引用
收藏
页码:119 / 134
页数:16
相关论文
共 50 条
[31]   Risk allocation in public-private partnership water supply projects in Ghana [J].
Ameyaw, Effah Ernest ;
Chan, Albert P. C. .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2015, 33 (03) :187-208
[32]   Risk Factors of Public-Private Partnership Projects in China: Comparison between the Water, Power, and Transportation Sectors [J].
Cheung, Esther ;
Chan, Albert P. C. .
JOURNAL OF URBAN PLANNING AND DEVELOPMENT, 2011, 137 (04) :409-415
[33]   Perception of Residual Value Risk in Public Private Partnership Projects: Critical Review [J].
Yuan, Jingfeng ;
Chan, Albert P. C. ;
Xiong, Wei ;
Skibniewski, Miroslaw J. ;
Li, Qiming .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (03)
[34]   RISK MANAGEMENT AT REALIZATION OF INFRASTRUCTURE PROJECTS UNDER PUBLIC-PRIVATE PARTNERSHIP [J].
Hrytsenko, L. L. ;
Krasulya, T. Y. .
ACTUAL PROBLEMS OF ECONOMICS, 2011, (126) :85-90
[35]   Procurement innovation for public construction projects A study of agent-construction system and public-private partnership in China [J].
Lu Weisheng ;
Liu, Anita M. M. ;
Wang Hongdi ;
Wu Zhongbing .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2013, 20 (06) :543-+
[36]   Investigating the Driving Factors of Public Participation in Public-Private Partnership (PPP) Projects-A Case Study of China [J].
Luo, Ziqian ;
Li, Junjie ;
Wu, Zezhou ;
Li, Shenghan ;
Bi, Guoqiang .
INTERNATIONAL JOURNAL OF ENVIRONMENTAL RESEARCH AND PUBLIC HEALTH, 2022, 19 (09)
[37]   Social Responsibility Initiatives for Public-Private Partnership Projects: A Comparative Study between China and Ghana [J].
Osei-Kyei, Robert ;
Chan, Albert P. C. ;
Yu, Yao ;
Chen, Chuan ;
Ke, Yongjian ;
Tijani, Bashir .
SUSTAINABILITY, 2019, 11 (05)
[38]   USING FUZZY ANALYTIC NETWORK PROCESS AND ISM METHODS FOR RISK ASSESSMENT OF PUBLIC-PRIVATE PARTNERSHIP: A CHINA PERSPECTIVE [J].
Li, Yan ;
Wang, Xinyu .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2019, 25 (02) :168-183
[39]   Spatial Characteristics and Driving Factors of Public-Private Partnership Projects Implemented in China [J].
Yang, Fan ;
Li, Jintao ;
Wang, Yi ;
Guo, Shengyu ;
Lei, Heqian .
BUILDINGS, 2022, 12 (06)
[40]   Public private partnership in brownfield remediation projects in China: Identification and structure analysis of risks [J].
Han, Qingye ;
Zhu, Yuming ;
Ke, Ginger Y. ;
Hipel, Keith W. .
LAND USE POLICY, 2019, 84 :87-104