Machine Learning-Based Prediction of Missing Components for Assembly - a Case Study at an Engineer-to-Order Manufacturer

被引:9
作者
Burggraef, Peter [1 ]
Wagner, Johannes [1 ]
Heinbach, Benjamin [1 ]
Steinberg, Fabian [1 ]
机构
[1] Univ Siegen, Dept Mech Engn, Chair Int Prod Engn & Management IPEM, D-57076 Siegen, Germany
关键词
Predictive models; Data models; Production; Manufacturing; Companies; Analytical models; Schedules; Production control; assembly; prediction methods; lead time reduction; machine learning; supervised learning; classification algorithms; regression analysis; data analysis; LEAD TIME PREDICTION; PERFORMANCE; ENVIRONMENT; REGRESSION; VOLUME;
D O I
10.1109/ACCESS.2021.3075620
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
For manufacturing companies, especially for machine and plant manufacturers, the assembly of products in time has an essential impact on meeting delivery dates. Often missing individual components lead to a delayed assembly start, hereinafter referred to as assembly start delayers. Identifying the assembly start delayers early in the production process can help to set countermeasures to meet the required delivery dates. In order to achieve this, we set up 24 prediction models on four different levels of detail utilizing different machine learning-algorithms - six prediction models on every level of detail - and applying a case-based research approach in order to identify the model with the highest model quality. The modeling approach on the four levels of detail is different. The models on the coarsest level of detail predict assembly start delayers utilizing a classification approach. The models on the three finer levels of detail predict assembly start delayers via a regression of different lead times and subsequent postprocessing operations to identify the assembly start delayers. After training of the 24 prediction models based on a real data set of a machine and plant manufacturer and evaluating their model quality, the classification model utilizing a Gradient Boosting classifier showed best results. Thus, performing a binary classification to identify assembly start delayers was the best modelling approach. With the achieved results, our study is a first approach to predict assembly start delayers and gives insights in the performance of different modeling approaches in the area of a production planning and control.
引用
收藏
页码:105926 / 105938
页数:13
相关论文
共 58 条
[1]  
Agarap A. F., 2019, DEEP LEARNING USING
[2]   Real-time prediction of order flowtimes using support vector regression [J].
Alenezi, Abdulrahman ;
Moses, Scott A. ;
Trafalis, Theodore B. .
COMPUTERS & OPERATIONS RESEARCH, 2008, 35 (11) :3489-3503
[3]  
[Anonymous], 2006, P 23 INT C MACH LEAR, DOI 10.1145/1143844.1143874
[4]   Artificial neural networks: fundamentals, computing, design, and application [J].
Basheer, IA ;
Hajmeer, M .
JOURNAL OF MICROBIOLOGICAL METHODS, 2000, 43 (01) :3-31
[5]  
Berlec T, 2008, STROJ VESTN-J MECH E, V54, P308
[6]   Approaches for the Prediction of Lead Times in an Engineer to Order Environment-A Systematic Review [J].
Burggraef, Peter ;
Wagner, Johannes ;
Koke, Benjamin ;
Steinberg, Fabian .
IEEE ACCESS, 2020, 8 :142434-142445
[7]  
Burggräf P, 2018, 2018 INTERNATIONAL CONFERENCE ON INFORMATION MANAGEMENT AND PROCESSING (ICIMP 2018), P82, DOI 10.1109/ICIMP1.2018.8325846
[8]   Cost-benefit analysis for disruption prevention in low-volume assembly [J].
Burggräf P. ;
Wagner J. ;
Lück K. ;
Adlon T. .
Production Engineering, 2017, 11 (03) :331-342
[9]   SURVEY OF SCHEDULING RESEARCH INVOLVING DUE DATE DETERMINATION DECISIONS [J].
CHENG, TCE ;
GUPTA, MC .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1989, 38 (02) :156-166
[10]   The advantages of the Matthews correlation coefficient (MCC) over F1 score and accuracy in binary classification evaluation [J].
Chicco, Davide ;
Jurman, Giuseppe .
BMC GENOMICS, 2020, 21 (01)