Simulation-based solution for a dynamic multi-crane-scheduling problem in a steelmaking shop

被引:18
作者
Li, Ji [1 ]
Xu, Anjun [1 ]
Zang, Xuesong [1 ]
机构
[1] Univ Sci & Technol Beijing, Sch Met & Ecol Engn, Beijing, Peoples R China
基金
中国国家自然科学基金;
关键词
Crane scheduling; predictive-reactive rescheduling; simulation; heuristic; steelmaking shop; GENETIC ALGORITHM; HOISTS;
D O I
10.1080/00207543.2019.1687952
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Here, we present a simulation-based solution for a multi-crane-scheduling problem derived from a steelmaking shop. This problem features non-conflict constraint between cranes, station-capacity constraint, and jobs with inaccurate release times and different temporal scheduling objectives. The predictive-reactive rescheduling strategy was applied to solve the problem. The problem was modelled considering different temporal objectives for the jobs and workload objective for the cranes and the model was solved by a heuristic. In the simulation, the jobs were not directly given but generated by a job-prediction method. The cranes' moving behaviours were controlled by a designed crane trajectory solution. Experimental tests were conducted using data from the site and the results show that the proposed crane-scheduling solution provided better scheduling results than both the exhaustive method and the method that is used in the production field. The best predictive spans for the jobs in this specific crane-scheduling problem were found to be 7-14 min. The real-time performance of the crane-scheduling solution is demonstrated to highly guarantee its practicability.
引用
收藏
页码:6970 / 6984
页数:15
相关论文
共 32 条
[1]   A Multi-Agent Based Simulation Model for Rail-Rail Transshipment: An Engineering Approach for Gantry Crane Scheduling [J].
Abourraja, Mohamed Nezar ;
Oudani, Mustapha ;
Samiri, Mohamed Yassine ;
Boudebous, Dalila ;
El Fazziki, Abdelaziz ;
Najib, Mehdi ;
Bouain, Abdelhadi ;
Rouky, Naoufal .
IEEE ACCESS, 2017, 5 :13142-13156
[2]   A simulation-based Genetic Algorithm approach for the quay crane scheduling under uncertainty [J].
Al-Dhaheri, Noura ;
Jebali, Aida ;
Diabat, Ali .
SIMULATION MODELLING PRACTICE AND THEORY, 2016, 66 :122-138
[3]  
Aron I., 2011, 12 INFORMS COMP SOC
[4]   A fast heuristic for quay crane scheduling with interference constraints [J].
Bierwirth, Christian ;
Meisel, Frank .
JOURNAL OF SCHEDULING, 2009, 12 (04) :345-360
[5]   Determining crane areas in intermodal transshipment yards: The yard partition problem [J].
Boysen, Nils ;
Fliedner, Malte .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2010, 204 (02) :336-342
[6]   An Improved Mixed Integer Programming Approach for Multi-Hoist Cyclic Scheduling Problem [J].
Che, Ada ;
Lei, Weidong ;
Feng, Jianguang ;
Chu, Chengbin .
IEEE TRANSACTIONS ON AUTOMATION SCIENCE AND ENGINEERING, 2014, 11 (01) :302-309
[7]   Multiple yard cranes scheduling for loading operations in a container terminal [J].
Chen, Lu ;
Langevin, Andre .
ENGINEERING OPTIMIZATION, 2011, 43 (11) :1205-1221
[8]   A Branch-and-Cut algorithm for factory crane scheduling problem [J].
Cheng, Xu ;
Tang, Lixin ;
Pardalos, Panos M. .
JOURNAL OF GLOBAL OPTIMIZATION, 2015, 63 (04) :729-755
[9]   A workload balancing genetic algorithm for the quay crane scheduling problem [J].
Chung, S. H. ;
Chan, Felix T. S. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2013, 51 (16) :4820-4834
[10]   Optimising the Slab Yard Planning and Crane Scheduling Problem using a two-stage heuristic [J].
Dohn, Anders ;
Clausen, Jens .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2010, 48 (15) :4585-4608