Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia

被引:19
作者
Alhajri, Abdullah Rasheed [1 ]
Alshibani, Adel [2 ]
机构
[1] KFUPM, Construct Engn & Management, Dhahran 31261, Saudi Arabia
[2] Architectural Engn Dept KFUPM, Dhahran 31261, Saudi Arabia
关键词
petrochemical projects; critical factors; schedule delay;
D O I
10.3390/en11071652
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
This paper presents a study conducted to identify, assess, rank, and compare the most influencing factors causing schedule delays during the construction phase of petrochemical projects in Saudi Arabia. The methodology followed in this research to achieve the main aims is a combination of the comprehensive review of the literature and the interviewing of a number of local experts, which have resulted in identifying 23 factors. A total of 90 completed responses were gathered from 106 received responses. The study found that the most influencing factors causing schedule delays during the construction of petrochemical projects in Saudi Arabia are "Poor site management and supervision by contractors"; "Conflict between the main contractor and subcontractor"; "Poor planning and scheduling of projects by the contractor"; "Delays in material or equipment delivery"; and followed by "Delays in Handing Over Construction Site to the Contractor". This paper is original in the sense that the areas of knowledge and practice covered in the identified factors were distributed and not available in one source. The factors are derived from personal interviews with selected project managers, project engineers, construction supervisors, and the others from different positions in the project department and from the relevant literature.
引用
收藏
页数:18
相关论文
共 15 条
[1]  
Alinaitwe H, 2013, J CONSTR DEV CTRIES, V18, P33
[2]  
[Anonymous], 2016, Journal of Construction in Developing Countries, V21, P51, DOI [DOI 10.21315/JCDC2016.21.1.4, 10.21315/jcdc2016.21.1]
[3]   Analysing factors affecting delays in Indian construction projects [J].
Doloi, Hemanta ;
Sawhney, Anil ;
Iyer, K. C. ;
Rentala, Sameer .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2012, 30 (04) :479-489
[4]  
Gunduz, 2016, J CIV ENV STRUCT ARC, V10, P531
[5]   COMPARISON OF SCHEDULE DELAY AND CAUSAL FACTORS BETWEEN TRADITIONAL AND GREEN CONSTRUCTION PROJECTS [J].
Hwang, Bon Gang ;
Leong, Lay Peng .
TECHNOLOGICAL AND ECONOMIC DEVELOPMENT OF ECONOMY, 2013, 19 (02) :310-330
[6]   Rework and schedule performance A profile of incidence, impact, causes and solutions [J].
Hwang, Bon-Gang ;
Yang, Shimin .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2014, 21 (02) :190-+
[7]   Identifying the critical factors affecting schedule performance of public housing projects [J].
Hwang, Bon-Gang ;
Zhao, Xianbo ;
Ng, Si Yi .
HABITAT INTERNATIONAL, 2013, 38 :214-221
[8]  
Khan S., 2015, P PROJ MAN RED IND B
[9]  
Othuman Mydin M.O., 2014, EDP SCI
[10]  
Rao B.P., 2016, Journal of Information Technology and Economic Development, V7, P15